Construction progress in September 2025
02.10.2025
Go back
Sharing the latest news from the construction site for September:
Building #3, section 1:
- painting ceilings under the cube-shaped rail - 100%;
- ongoing work on installing fire alarm system;
- work in progress on lobby decoration (plastering) - 80%;
- work in progress on laying ceramic tiles on balconies - 10%;
- installation of air conditioning system in lobby has started.
Building #3, section 2:
- work in progress on laying ceramic tiles on balconies - 100%;
- painting ceilings under the cube-shaped rail - 100%.
Building #3, section 3:
- decorative wall plastering (with painting) - 100%;
- laying ceramic tiles on floors and walls of MZK from 18th to 34th floor - 85%.
Parking garage #3:
waterproofing works of the parking slab: installation of junctions, pouring lightweight concrete, membrane installation, drainage membrane and geotextile, reinforcement of protective slab and concreting - 100%;
ongoing work on laying parking floor.
Building #4, section 1:
- brickwork of walls from 1st to 32nd floor - 93%, from 33rd to 34th floor - 55%.
Building #4, section 2:
- brickwork of walls from 8th to 11th floor - 40%.
Building #4, section 3:
- brickwork of walls on the 11th floor.
Building #4, section 5:
- brickwork of walls on the 12th floor.
Parking garage #4:
- waterproofing works of piles, beams, and slab waterproofing - 50%;
- ongoing work on vertical constructions of parking - 75%, floor slab - 45%.