Construction progress in September 2025

02.10.2025

Go back

Sharing the latest news from the construction site for September:

Building #3, section 1:

  • painting ceilings under the cube-shaped rail - 100%;
  • ongoing work on installing fire alarm system;
  • work in progress on lobby decoration (plastering) - 80%;
  • work in progress on laying ceramic tiles on balconies - 10%;
  • installation of air conditioning system in lobby has started.

Building #3, section 2:

  • work in progress on laying ceramic tiles on balconies - 100%;
  • painting ceilings under the cube-shaped rail - 100%.

Building #3, section 3:

  • decorative wall plastering (with painting) - 100%;
  • laying ceramic tiles on floors and walls of MZK from 18th to 34th floor - 85%.

Parking garage #3:

    waterproofing works of the parking slab: installation of junctions, pouring lightweight concrete, membrane installation, drainage membrane and geotextile, reinforcement of protective slab and concreting - 100%;

    ongoing work on laying parking floor.

Building #4, section 1:

  • brickwork of walls from 1st to 32nd floor - 93%, from 33rd to 34th floor - 55%.

Building #4, section 2:

  • brickwork of walls from 8th to 11th floor - 40%.

Building #4, section 3:

  • brickwork of walls on the 11th floor.

Building #4, section 5:

  • brickwork of walls on the 12th floor.

Parking garage #4:

  • waterproofing works of piles, beams, and slab waterproofing - 50%;
  • ongoing work on vertical constructions of parking - 75%, floor slab - 45%.