Construction progress for December 2025

05.01.2026

Go back

Sharing the latest news from the construction site for December:

Building No. 3, section 1:

  • work is in progress on decorating the lobby and installing suspended ceilings with drywall framework – 50%;
  • installation of lobby air conditioning system – 97%.

Building No. 3, section 2:

  • work in progress on decorating staircases – 65%;
  • installation of ceilings with cubic rail suspended ceiling system – 100%.

Building No. 3, section 3:

  • lobby decoration work (wall plastering) – 100%;
  • lobby work continues with installation of suspended ceilings with drywall framework – 30%;
  • installation of apartment electricity meters – 40%.

Parking lot No. 3:

  • facade cladding of parking exit – 60%;
  • floor works in parking lot (grinding of diffusion joints, waterproofing and laying of fiberboard flooring) – 40%.

Improvement of zone 1 in Building No. 3:

  • earthworks in progress – 90%;
  • construction of RP, concrete works – 60%, masonry – 10%;
  • foundation waterproofing – 80%.

Building No. 4, section 1:

  • brick wall masonry on 33rd and 34th floors – 90%.

Building No. 4, section 2:

  • brick wall masonry on technical floor – 100%.

Parking lot No. 4:

  • waterproofing works for piles, beams, and beam slab in progress – 100%;
  • vertical construction works in progress for parking – 90%, floor slab – 80%.
  • backfilling of parking beams – 90%.