Construction progress for December 2025
05.01.2026
Go back
Sharing the latest news from the construction site for December:
Building #3, section 1:
- works are being carried out for the decoration of the lobby and installation of suspended ceilings with GKLW (framework) - 50%;
- installation of air conditioning system in the lobby - 97%.
Building #3, section 2:
- works for the decoration of the staircases - 65%;
- installation of MZK ceilings with cuboid rails - 100%.
Building #3, section 3:
- works for the decoration of the lobby (wall plastering) - 100%;
- ongoing work in the lobby for the installation of suspended ceilings with GKLW (framework) - 30%;
- installation of apartment electricity meters - 40%.
Parking building #3:
- facade cladding of the emergency exit from the parking lot - 60%;
- flooring works in the parking lot (grinding of diffusion joints, waterproofing and laying of fibroconcrete floors) - 40%.
Land improvement of zone 1 in building #3:
- earthworks in progress;
- construction of RP, monolithic works - 60%, masonry - 10%.
Building #4, section 1:
- brickwork of walls on the 33rd and 34th floors - 63%.
Building #4, section 2:
- brickwork of walls on the technical floor - 100%.
Parking building #4:
- waterproofing of piles, rafters and rafter slab - 75% in progress;
- ongoing work on the installation of vertical structures of the parking lot - 87%, slab construction - 68%.







































































































