Construction progress for December 2025
05.01.2026
Go back
Sharing the latest news from the construction site for December:
Building No. 3, section 1:
- work is in progress on decorating the lobby and installing suspended ceilings with drywall framework – 50%;
- installation of lobby air conditioning system – 97%.
Building No. 3, section 2:
- work in progress on decorating staircases – 65%;
- installation of ceilings with cubic rail suspended ceiling system – 100%.
Building No. 3, section 3:
- lobby decoration work (wall plastering) – 100%;
- lobby work continues with installation of suspended ceilings with drywall framework – 30%;
- installation of apartment electricity meters – 40%.
Parking lot No. 3:
- facade cladding of parking exit – 60%;
- floor works in parking lot (grinding of diffusion joints, waterproofing and laying of fiberboard flooring) – 40%.
Improvement of zone 1 in Building No. 3:
- earthworks in progress – 90%;
- construction of RP, concrete works – 60%, masonry – 10%;
- foundation waterproofing – 80%.
Building No. 4, section 1:
- brick wall masonry on 33rd and 34th floors – 90%.
Building No. 4, section 2:
- brick wall masonry on technical floor – 100%.
Parking lot No. 4:
- waterproofing works for piles, beams, and beam slab in progress – 100%;
- vertical construction works in progress for parking – 90%, floor slab – 80%.
- backfilling of parking beams – 90%.