Sharing the latest news from the construction site for October:
Building No. 3, section 1:
- installation of fire alarm system in progress;
- plastering works in the lobby – 100%;
- laying ceramic tiles on balconies – 80%;
- installation of air conditioning system in the lobby – 10%.
Building No. 3, section 2:
- plastering works in the lobby – 100%;
- plastering works completed in commercial premises;
- decorating staircases – 40%.
Building No. 3, section 3:
- completed laying ceramic tiles on floors and walls of residential units from 3rd to 34th floor – 100%;
- decorating works in the lobby started;
- plastering works completed in commercial premises.
Parking Garage No. 3:
- insulation and cladding of the garage evacuation exit facade – 20%;
- ongoing work on the floor of the garage (grinding differential joints and waterproofing).
Landscaping of Zone 1 Parking Garage No. 3:
- earthworks in progress.
Building No. 4, section 1:
- brickwork on walls from 1st to 32nd floor – 95%, in progress from 33rd to 34th floor – 57%.
Building No. 4, section 2:
- brickwork on walls from 2nd to 10th floor – 100%, in progress on 11th floor – 90%.
Building No. 4, section 3:
- brickwork on walls on 11th floor ongoing.
Building No. 4, section 5:
- installation of ventilation blocks on the 14th floor in progress.
Parking Garage No. 4:
- waterproofing of columns, ramps, and ramp slab in progress – 60%;
- ongoing work on vertical structures of the garage – 80%, slab roofing – 50%.