Sharing the latest news from the construction site for October:

Building No. 3, section 1:

  • installation of fire alarm system in progress;
  • plastering works in the lobby – 100%;
  • laying ceramic tiles on balconies – 80%;
  • installation of air conditioning system in the lobby – 10%.

Building No. 3, section 2:

  • plastering works in the lobby – 100%;
  • plastering works completed in commercial premises;
  • decorating staircases – 40%.

Building No. 3, section 3:

  • completed laying ceramic tiles on floors and walls of residential units from 3rd to 34th floor – 100%;
  • decorating works in the lobby started;
  • plastering works completed in commercial premises.

Parking Garage No. 3:

  • insulation and cladding of the garage evacuation exit facade – 20%;
  • ongoing work on the floor of the garage (grinding differential joints and waterproofing).

Landscaping of Zone 1 Parking Garage No. 3:

  • earthworks in progress.

Building No. 4, section 1:

  • brickwork on walls from 1st to 32nd floor – 95%, in progress from 33rd to 34th floor – 57%.

Building No. 4, section 2:

  • brickwork on walls from 2nd to 10th floor – 100%, in progress on 11th floor – 90%.

Building No. 4, section 3:

  • brickwork on walls on 11th floor ongoing.

Building No. 4, section 5:

  • installation of ventilation blocks on the 14th floor in progress.

Parking Garage No. 4:

  • waterproofing of columns, ramps, and ramp slab in progress – 60%;
  • ongoing work on vertical structures of the garage – 80%, slab roofing – 50%.