OLEGIV Podil
Construction progress for December 2023

26.12.2023

Go back

OLEGIV Podil by DIM is under active construction.

In December, the following works were performed at the construction site:

Section 1:

  • Reinforcement of concreting of vertical structures up to -0.000 - 75%

Section 3:

  • Reinforcement of concreting of vertical structures up to -0.000 - 90%

Section 4:

  • Reinforcement of concreting of vertical structures up to -0.000 - 90% (lower part)

  • Reinforcement of concreting of the floor slab of the lower part of the building -4.950 – 28%

Parking I zone:

  • Backfilling, soil compaction, preparation of the area of the section for the installation of the power plate - 80%

  • Reinforcement of concreting pits in the underground part - 100%

  • Reinforcement of concreting of the power plate - 75%

  • Reinforcement of concreting of vertical structures up to - 20% (lower part)

Parking II zone:

  • Concreting reinforcement of vertical structures up to -0.000 - 75% (lower part)

  • Reinforcement of concreting of the floor slab of the lower part of the building -4.950 – 25%