Construction Progress for August 2026

03.09.2026

Go back

MONOLITHIC WORKS

Main Building:

  • reinforcement of vertical structures on the 16th floor – 100%;
  • concreting of vertical structures on the 16th floor – 100%;
  • reinforcement of the 17th-floor slab – 100%;
  • concreting of the 17th-floor slab – 100%;
  • reinforcement of vertical structures on the 18th floor – 70%;
  • concreting of vertical structures on the 18th floor – 50%;
  • installation of precast reinforced concrete stair flights and landings, floors 15–17 – 100%;
  • installation of ventilation blocks, floors 13–16 – 100%.

Left stylobate: no changes. Right stylobate: no changes.

During August, 623 m³ of reinforced concrete structures of the building frame were completed.

MASONRY WORKS

Main Building:

  • masonry works for the walls of the 3rd floor – 50%.