Construction Progress for August 2026
03.09.2026
Go back
MONOLITHIC WORKS
Main Building:
- reinforcement of vertical structures on the 16th floor – 100%;
- concreting of vertical structures on the 16th floor – 100%;
- reinforcement of the 17th-floor slab – 100%;
- concreting of the 17th-floor slab – 100%;
- reinforcement of vertical structures on the 18th floor – 70%;
- concreting of vertical structures on the 18th floor – 50%;
- installation of precast reinforced concrete stair flights and landings, floors 15–17 – 100%;
- installation of ventilation blocks, floors 13–16 – 100%.
Left stylobate: no changes. Right stylobate: no changes.
During August, 623 m³ of reinforced concrete structures of the building frame were completed.
MASONRY WORKS
Main Building:
- masonry works for the walls of the 3rd floor – 50%.