THE ONE Construction Progress – July 2026

MONOLITHIC WORKS

Main Building:

  • Reinforcement of the 14th-floor slab — 100%;
  • Concreting of the 14th-floor slab — 100%;
  • Reinforcement of the 15th-floor vertical structures — 100%;
  • Concreting of the 15th-floor vertical structures — 100%;
  • Reinforcement of the 15th-floor slab — 100%;
  • Concreting of the 15th-floor slab — 100%;
  • Reinforcement of the 16th-floor vertical structures — 50%;
  • Installation of precast reinforced concrete stair flights and landings, floors 12–15 — 100%;
  • Installation of ventilation blocks, floors 11–13 — 100%.

Left Stylobate: No changes.

Right Stylobate: No changes.

Completed in July: 675 m³ of reinforced concrete structural frame.

MASONRY WORKS

Main Building:

  • Masonry of the 3rd-floor walls — 100%.