Construction Progress for July 2026
03.08.2026
Go back
THE ONE Construction Progress – July 2026
MONOLITHIC WORKS
Main Building:
- Reinforcement of the 14th-floor slab — 100%;
- Concreting of the 14th-floor slab — 100%;
- Reinforcement of the 15th-floor vertical structures — 100%;
- Concreting of the 15th-floor vertical structures — 100%;
- Reinforcement of the 15th-floor slab — 100%;
- Concreting of the 15th-floor slab — 100%;
- Reinforcement of the 16th-floor vertical structures — 50%;
- Installation of precast reinforced concrete stair flights and landings, floors 12–15 — 100%;
- Installation of ventilation blocks, floors 11–13 — 100%.
Left Stylobate: No changes.
Right Stylobate: No changes.
Completed in July: 675 m³ of reinforced concrete structural frame.
MASONRY WORKS
Main Building:
- Masonry of the 3rd-floor walls — 100%.