Construction Progress for October 2026

02.11.2026

Go back

Building Ahead — THE ONE October Progress Update

In October, we continued constructing the reinforced concrete frame of the main building. Concreting of the 20th-floor slab and the vertical structures of the 21st floor was completed. At the same time, work on the 21st-floor slab is ongoing, and reinforcement of the vertical structures on the 22nd floor has begun.

  • A total of 420 m³ of reinforced concrete structures for the building frame were completed during the month. Here is a detailed overview of construction progress as of the end of October 2026. Main Building At the 19th–20th floor levels, work on the floor slabs and vertical structures was completed, and precast stair components were installed.
  • Concreting of the 19th-floor slab is 100% complete.
  • Reinforcement and concreting of the 20th-floor vertical structures have been completed.
  • Reinforcement and concreting of the 20th-floor slab have been completed.
  • Installation of precast reinforced concrete stair flights and landings on the 19th–20th floors is 100% complete.

On the 21st floor, the vertical structures have been completed, and work on the floor slab is ongoing. At the same time, reinforcement of the structures on the next floor is underway.

  • Reinforcement and concreting of the 21st-floor vertical structures have been completed.
  • Reinforcement of the 21st-floor slab is 35% complete.
  • Concreting of the 21st-floor slab is 35% complete.
  • Reinforcement of the 22nd-floor vertical structures is 20% complete.
  • Alongside construction of the building frame, we are installing ventilation blocks. Installation on the 18th and 19th floors is 100% complete.

The building frame is taking shape step by step: from structural reinforcement to concreting and moving on to the next level. Behind every floor is the daily work of our team. We continue building THE ONE and keeping you informed of our progress.