Construction progress for February 2026
04.03.2026
Go back
Construction results for THE ONE in February 2026:
Main building:
- reinforcement of vertical structures on the 4th floor - 100%
- concreting of vertical structures on the 4th floor - 100%
- reinforcement of the slab of the 4th floor - 100%
- concreting of the slab of the 4th floor - 100%
- reinforcement of vertical structures on the 5th floor - 60%
- concreting of vertical structures on the 5th floor - 40%
- installation of prefabricated reinforced concrete stairs and platforms on the 4th floor - 100%
- installation of ventilation blocks on the 2nd floor - 100%
Completed in February - 453 m3 of reinforced concrete building frame structures.