Construction results for THE ONE in February 2026:

Main building:

  • reinforcement of vertical structures on the 4th floor - 100%
  • concreting of vertical structures on the 4th floor - 100%
  • reinforcement of the slab of the 4th floor - 100%
  • concreting of the slab of the 4th floor - 100%
  • reinforcement of vertical structures on the 5th floor - 60%
  • concreting of vertical structures on the 5th floor - 40%
  • installation of prefabricated reinforced concrete stairs and platforms on the 4th floor - 100%
  • installation of ventilation blocks on the 2nd floor - 100%

Completed in February - 453 m3 of reinforced concrete building frame structures.