THE ONE
Construction Progress for June 2026

01.07.2026

Go back

THE ONE Construction Progress – June 2026

Monolithic Works

Main Building

Concreting of vertical structural elements on the 11th floor – 100%; Reinforcement of the 11th-floor slab – 100%; Concreting of the 11th-floor slab – 100%; Reinforcement of vertical structural elements on the 12th floor – 100%; Concreting of vertical structural elements on the 12th floor – 100%; Reinforcement of the 12th-floor slab – 100%; Concreting of the 12th-floor slab – 100%; Reinforcement of vertical structural elements on the 13th floor – 100%; Concreting of vertical structural elements on the 13th floor – 100%; Reinforcement of the 13th-floor slab – 100%; Concreting of the 13th-floor slab – 100%; Reinforcement of the 14th-floor slab – 10%; Installation of precast reinforced concrete stair flights and landings on Floors 10–12 – 100%; Installation of ventilation blocks on Floors 10–11 – 100%.

Left Stylobate

No changes. Right Stylobate

No changes.

Completed in June: 680 m³ of reinforced concrete structural frame.