Construction results of THE ONE for March 2026:

CONCRETE WORKS

Main building:

  • reinforcement and concreting of vertical structures on the 5th floor – 100%
  • reinforcement and concreting of the slab on the 5th floor – 100%
  • reinforcement and concreting of vertical structures on the 6th floor – 100%
  • reinforcement and concreting of the slab on the 6th floor – 100%
  • reinforcement and concreting of vertical structures on the 7th floor – 30%
  • installation of precast reinforced concrete stairs and platforms on the 5th floor – 100%
  • installation of ventilation units on the 3rd and 4th floors – 100%

Left stylobate:

  • concreting of the retaining wall on the 2nd floor – 100%
  • reinforcement and concreting of the slab on the 2nd floor – 100%

MASONRY WORKS

  • masonry works on the 2nd floor – 30%

Completedfor the month of March – 630m³of reinforced concrete structures of the building frame.