Construction progress for March 2026
03.04.2026
Go back
Construction results of THE ONE for March 2026:
CONCRETE WORKS
Main building:
- reinforcement and concreting of vertical structures on the 5th floor – 100%
- reinforcement and concreting of the slab on the 5th floor – 100%
- reinforcement and concreting of vertical structures on the 6th floor – 100%
- reinforcement and concreting of the slab on the 6th floor – 100%
- reinforcement and concreting of vertical structures on the 7th floor – 30%
- installation of precast reinforced concrete stairs and platforms on the 5th floor – 100%
- installation of ventilation units on the 3rd and 4th floors – 100%
Left stylobate:
- concreting of the retaining wall on the 2nd floor – 100%
- reinforcement and concreting of the slab on the 2nd floor – 100%
MASONRY WORKS
- masonry works on the 2nd floor – 30%
Completedfor the month of March – 630m³of reinforced concrete structures of the building frame.