Construction progress for May 2026

01.06.2026

Go back

THE ONE construction results for May 2026:

Main building:

  • reinforcement of vertical structures on the 9th floor — 100% concreting of vertical structures on the 9th floor — 100% reinforcement of the 9th-floor slab — 100% concreting of the 9th-floor slab — 100%
  • reinforcement of vertical structures on the 10th floor — 100% concreting of vertical structures on the 10th floor — 100% reinforcement of the 10th-floor slab — 100% concreting of the 10th-floor slab — 100%
  • reinforcement of vertical structures on the 11th floor — 100% concreting of vertical structures on the 11th floor — 65% reinforcement of the 11th-floor slab — 45% concreting of the 11th-floor slab — 45%
  • installation of precast reinforced concrete stair flights and landings, floors 8–10 — 100% installation of ventilation blocks, floors 7–9 — 100%

Completed in May — 740 m³ of reinforced concrete structures of the building frame.