Construction progress for January 2026
29.01.2026
Go back
Construction results of THE ONE for January 2026:
Main building:
- reinforcement of vertical structures of the 3rd floor - 100%
- concreting of vertical structures of the 3rd floor - 100% reinforcement of the slab of the 3rd floor - 100% concreting of the slab of the 3rd floor - 100%
- reinforcement of vertical structures of the 4th floor - 35%
- concreting of vertical structures of the 4th floor - 25%
- installation of prefabricated reinforced concrete stairs and platforms on the 2nd floor - 100%
Completedfor the month of January - 312 m3of reinforced concrete structures of the building frame.