Construction progress for January 2026

29.01.2026

Go back

Construction results of THE ONE for January 2026:

Main building:

  • reinforcement of vertical structures of the 3rd floor - 100%
  • concreting of vertical structures of the 3rd floor - 100% reinforcement of the slab of the 3rd floor - 100% concreting of the slab of the 3rd floor - 100%
  • reinforcement of vertical structures of the 4th floor - 35%
  • concreting of vertical structures of the 4th floor - 25%
  • installation of prefabricated reinforced concrete stairs and platforms on the 2nd floor - 100%

Completedfor the month of January - 312 m3of reinforced concrete structures of the building frame.