A136 Highlight Tower
Construction progress for August 2023

24.08.2023

Go back

A136 Highlight Tower from DIM is under active construction.

We share the latest news from the construction site for August:

  • The floor slab of the 33rd floor has been installed - 100%.

  • Reinforcement of elements of the 34th floor - 15%.

  • Brickwork from -2nd to 23rd floor has been completed - 90%.

  • Brickwork from the 24th to the 30th floor has been completed - 36%.

  • The floor screed on the 9th floor has been completed - 93%.

  • Completed plumbing works from -2 to 27th floor - 35%.

  • Electrical installation works from -2nd to 27th floor have been completed - 45%.

  • The smoke removal system of floors -2 and -1 was completed - 58%.

  • The ventilation system of floors -2 and -1 was completed - 50%.

  • Automatic fire extinguishing system from -2nd to 5th floor - 82%.

  • 95% of SPOK stained glass systems from the 6th to the 15th floor have been installed.

  • 95% of the double-glazed windows of the stained-glass systems from the 6th to the 15th floor have been installed.

  • 85% of the window structures from the 15th to the 24th floor have been installed.

  • 15% of double-glazed units of window structures from the 15th to the 24th floor have been installed.

  • 85% of SPOK stained glass systems from the 15th to the 24th floor have been installed.

  • 65% of the double-glazed windows of the stained-glass systems from the 15th to the 24th floor have been installed.

  • 96% of SPOK stained glass systems from the 1st to the 4th floor have been installed.

  • 95% of the double-glazed windows of the stained glass systems from the 1st to the 4th floor have been installed.

  • The roof is arranged on the 2, 3, 4, 5 floors - 45%.

  • 37% of the facing of the stylobate facade has been arranged (insulation, subsystem, installation of decorative stone "Travertine").

  • The installation of the hinged ventilated facade from the 5th to the 24th floor has been completed - 80%.

  • Work on lighting the facade of the stylobate, 1st-5th floor, has been completed - 52%.

  • Work on lighting the facade of the 5th-15th floor has been completed - 30%.