Construction progress for October 2023
24.10.2023
A136 Highlight Tower by DIM is being built at a fast pace!
We share the latest news from the construction site for October:
The vertical elements of the 34th floor are arranged - 100%.
Ventilation units up to the 30th floor have been installed.
Brickwork from -2 to 24th floor has been completed - 93%.
Brickwork from the 24th to the 31st floor has been completed - 45%.
Electrical installation works from -2nd to 27th floor have been completed - 40%.
Plastering of the technical premises and MZK -2 and -1 floor was completed - 45%.
60% of double-glazed units of window structures from the 15th to the 26th floor have been installed.
65% of SPOK stained glass systems from the 15th to the 26th floor have been installed.
45% of the double-glazed windows of the stained glass systems from the 15th to the 26th floor have been installed.
39% of the cladding of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine").
Works on 100% insertion of external networks (water supply) have been completed.
The installation of the hinged ventilated facade from the 5th to the 24th floor has been completed - 84%.
Installation of passenger elevators of the commercial part - 95%.