A136 Highlight Tower
Construction progress for September 2023

29.09.2023

Go back

A136 Highlight Tower by DIM is being built at a fast pace!

We share the latest news from the construction site for September:

  • The monolithic parapet of the 34th floor has been installed - 100%.

  • Brickwork from -2 to 24th floor has been completed - 92%.

  • Brickwork from the 24th to the 30th floor has been completed - 40%.

  • The floor screed on the 9th floor has been completed - 96%.

  • 95% of the window structures from the 15th to the 24th floor have been installed.

  • 17% of double-glazed units of window structures from the 15th to the 24th floor have been installed.

  • 87% of SPOK stained glass systems from the 15th to the 22nd floor have been installed.

  • 85% of the double-glazed windows of the stained-glass systems from the 15th to the 22nd floor have been installed.

  • 97% of SPOK stained glass systems from the 1st to the 4th floor have been installed.

  • 96% of the double-glazed windows of the stained glass systems from the 1st to the 4th floor have been installed.

  • 37% of the cladding of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine").

  • Works on 100% insertion of external networks (water supply) have been completed.

  • The installation of the hinged ventilated facade from the 5th to the 24th floor has been completed - 82%.