Construction progress for December 2023
13.12.2023
A136 Highlight Tower by DIM is being built at a fast pace!
We share the latest news from the construction site for December:
Mounted ventilation units to tech. floor
Brickwork from -2 to 24th floor has been completed - 95%.
Brickwork from the 24th to the 34th floor has been completed - 60%.
Completed plumbing works from -2 to 34 floor - 27%.
Plastering of technical premises and MZK -2 and -1 floor was completed - 47%.
69% of window structures from the 15th to the 34th floor have been installed.
64% of double-glazed units of window structures from the 15th to the 34th floor have been installed.
69% of SPOK stained glass systems from the 15th to the 34th floor have been installed.
45% of the double-glazed windows of the stained glass systems from the 15th to the 34th floor have been installed.
Work on 65% of external networks (sewage) was completed.
The installation of the hinged ventilated facade from the 5th to the 34th floor was completed - 29%.
The roof of the house is 40% fixed.