A136 Highlight Tower
Construction progress for December 2023

13.12.2023

Go back

A136 Highlight Tower by DIM is being built at a fast pace!

We share the latest news from the construction site for December:

  • Mounted ventilation units to tech. floor

  • Brickwork from -2 to 24th floor has been completed - 95%.

  • Brickwork from the 24th to the 34th floor has been completed - 60%.

  • Completed plumbing works from -2 to 34 floor - 27%.

  • Plastering of technical premises and MZK -2 and -1 floor was completed - 47%.

  • 69% of window structures from the 15th to the 34th floor have been installed.

  • 64% of double-glazed units of window structures from the 15th to the 34th floor have been installed.

  • 69% of SPOK stained glass systems from the 15th to the 34th floor have been installed.

  • 45% of the double-glazed windows of the stained glass systems from the 15th to the 34th floor have been installed.

  • Work on 65% of external networks (sewage) was completed.

  • The installation of the hinged ventilated facade from the 5th to the 34th floor was completed - 29%.

  • The roof of the house is 40% fixed.