A136 Highlight Tower
Construction progress for November 2023

17.11.2023

Go back

A136 Highlight Tower by DIM is being built at a fast pace!

We share the latest news from the construction site for November:

  • Stairs to the 34th floor have been installed.

  • The overlap of the 34th floor has been arranged - 100%.

  • The monolithic structures of the walls and parapet of the superstructure (35th floor) have been installed - 100%.

  • Ventilation units up to the 32nd floor have been installed.

  • Brickwork from -2 to 24th floor was completed - 94%.

  • Brickwork from the 24th to the 33rd floor has been completed - 46%.

  • The floor screed on the 9th floor has been completed - 92%.

  • Completed plumbing works from -2 to 34th floor - 25%.

  • Electrical installation works from -2nd to 27th floor have been completed - 45%.

  • Plastering of technical premises and MZK -2 and -1 floor was completed - 47%.

  • 65% of the window structures from the 15th to the 34th floor have been installed.

  • 63% of double-glazed units of window structures from the 15th to the 34th floor have been installed.

  • 58% of SPOK stained glass systems from the 15th to the 34th floor have been installed.

  • 26% of double-glazed units of stained glass systems from the 15th to the 34th floor have been installed.

  • The roof of the house is arranged - 10%.

  • 40% of the cladding of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine").

  • Work on 50% of external networks (sewage) was completed.

  • The installation of the hinged ventilated facade from the 5th to the 34th floor was completed - 28%.

  • Installation of passenger elevators of the commercial part - 96%.