Construction progress for November 2023
17.11.2023
A136 Highlight Tower by DIM is being built at a fast pace!
We share the latest news from the construction site for November:
Stairs to the 34th floor have been installed.
The overlap of the 34th floor has been arranged - 100%.
The monolithic structures of the walls and parapet of the superstructure (35th floor) have been installed - 100%.
Ventilation units up to the 32nd floor have been installed.
Brickwork from -2 to 24th floor was completed - 94%.
Brickwork from the 24th to the 33rd floor has been completed - 46%.
The floor screed on the 9th floor has been completed - 92%.
Completed plumbing works from -2 to 34th floor - 25%.
Electrical installation works from -2nd to 27th floor have been completed - 45%.
Plastering of technical premises and MZK -2 and -1 floor was completed - 47%.
65% of the window structures from the 15th to the 34th floor have been installed.
63% of double-glazed units of window structures from the 15th to the 34th floor have been installed.
58% of SPOK stained glass systems from the 15th to the 34th floor have been installed.
26% of double-glazed units of stained glass systems from the 15th to the 34th floor have been installed.
The roof of the house is arranged - 10%.
40% of the cladding of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine").
Work on 50% of external networks (sewage) was completed.
The installation of the hinged ventilated facade from the 5th to the 34th floor was completed - 28%.
Installation of passenger elevators of the commercial part - 96%.