A136 Highlight Tower
Construction progress for January 2023

25.01.2023

Go back

The innovative skyscraper A136 Highlight Tower from DIM does not stop for a moment! With each new floor, our conscientious builders are bringing the construction of the house closer to completion this year.

Our handsome house is built from the best building materials, using natural travertine stone, Reynaers aluminum heat-insulated profile, large-sized ceramic granite made in Italy.

We are proud of the high pace of construction and share with you a fresh photo report for January: The floor slab of the 24th floor has been installed - 100% The floor slab of the 25th floor has been installed - 40%; The formwork and reinforced floor slab of the 25th floor have been installed - 30% 20% of the vertical elements of the walls and columns on the 25th floor have been installed; Staircases up to the 24th floor have been installed

Ventilation units up to the 20th-21st floor have been installed; Brickwork from -2 to 15th floor was completed - 70%; Brickwork from the 16th to the 18th floor has been completed - 55%; Plumbing works from -2nd to 13th floor were completed - 39%; Completed electrical installation work from -2 to 13th floor - 30%; The smoke removal system of floors -2 and -1 was completed - 40%; The ventilation system of floors -2 and -1 was completed - 30%; Automatic fire extinguishing system from -2nd to 5th floor - 66%; Plastering of technical premises and MZK -2 and -1 floors - 45%; 95% of window structures from the 5th to the 15th floor have been installed; 95% of double-glazed windows of window structures from the 5th to the 15th floor have been installed; 82% of SPOK stained glass systems from the 6th to the 15th floor have been installed; 80% of the double-glazed windows of the stained-glass systems from the 6th to the 15th floor have been installed; 67% of SPOK stained glass systems from the 1st to the 4th floor have been installed; 43% of double-glazed units of stained glass systems from the 1st to the 4th floor have been installed. The roof on the stylobate of the 2nd, 3rd, 4th and 5th floors has been installed - 30%. 18% of the facing of the stylobate facade has been arranged (Insulation, subsystem installation of decorative stone "Travertine"). Work on 90% of external networks (water supply) was completed. Installation of hinged ventilated facade from 5th to 15th floor was completed - 5%. Preparatory work on lighting of the stylobate facade 1-5th floor - 25% was completed.