A136 Highlight Tower
Construction progress for July 2023

20.07.2023

Go back

A136 Highlight Tower by DIM is under construction. We share the latest news from the construction site for July:

  • The floor slab of the 33rd floor has been installed - 50%.

  • 100% of the vertical elements of the walls and columns on the 33rd floor have been installed.

  • Stairs to the 33rd floor have been installed.

  • Ventilation units up to the 29th floor have been installed.

  • Brickwork from the 16th to the 27th floor has been completed - 58%.

  • The floor screed on the 9th floor has been completed - 90%.

  • 65% of the window structures from the 15th to the 24th floor have been installed.

  • 10% of double-glazed units of window structures from the 15th to the 24th floor have been installed.

  • 35% of SPOK stained glass systems from the 15th to the 24th floor have been installed.

  • 15% of the double-glazed windows of the stained-glass systems from the 15th to the 24th floor have been installed.

  • 96% of SPOK stained glass systems from the 1st to the 4th floor have been installed.

  • 86% of the double-glazed windows of the stained-glass systems from the 1st to the 4th floor have been installed.

  • The roof is arranged on the stylobate of 2, 3, 4, 5 floors - 40%.

  • 32% of the cladding of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine").

  • The installation of the hinged ventilated facade from the 5th to the 15th floor has been completed - 76%.

  • Preparatory work on the lighting of the facade of the 5th-15th floor has been completed - 28%.