A136 Highlight Tower
Construction progress for May 2023

25.05.2023

Go back

A136 Highlight Tower by DIM is growing every day. We are constantly and quickly approaching the completion of monolithic works.

We share a detailed report from the construction site for May:

  • The floor slab of the 30th floor has been installed - 100%.

  • The floor slab of the 31st floor has been installed - 50%.

  • 100% of the vertical elements of the walls and columns on the 31st floor have been installed.

  • Stairways up to the 30th floor have been installed.

  • Ventilation units up to the 27th floor have been installed.

  • Brickwork from -2nd to 15th floor has been completed - 87%.

  • Brickwork is completed from the 16th to the 27th floor - 30%.

  • Completed plumbing works from -2 to 27th floor - 25%.

  • Completed electrical installation work from -2 to 27th floor - 20%.

  • The smoke removal system of floors -2 and -1 was completed - 55%.

  • The ventilation system of floors -2 and -1 was completed - 48%.

  • Automatic fire extinguishing system from -2nd to 5th floor - 79%.

  • Plastering of the technical premises and MZK -2 and -1 floors was completed - 67%.

  • 99% of window structures from the 5th to the 16th floor have been installed.

  • 99% of double-glazed units of window structures from the 5th to the 15th floor have been installed.

  • 92% of SPOK stained-glass systems have been installed from the 6th to the 15th floor.

  • 85% of the double-glazed windows of the stained-glass systems from the 6th to the 15th floor have been installed.

  • 90% of SPOK stained glass systems from the 1st to the 4th floor have been installed.

  • 78% of the double-glazed windows of the stained-glass systems from the 1st to the 4th floor have been installed.

  • The 2, 3, 4, 5 floors are covered with a stylobate roof - 38%.

  • 28% of the cladding of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine").

  • The installation of the hinged ventilated facade from the 5th to the 15th floor has been completed - 65%.

  • Preparatory work on lighting the facade of the stylobate 1-5 floors has been completed - 53%.

  • Preparatory work on the lighting of the facade of the 5th-15th floor has been completed - 23%.

  • Installation of passenger elevators of the commercial part - 95%.