A136 Highlight Tower
Construction progress for April 2024

29.04.2024

Go back

A136 Highlight Tower by DIM is being built at a fast pace!

We share the latest news from the construction site for April:

  • Brickwork from the 24th to the 33rd floor has been completed - 94%;
  • Plumbing connections of apartments 8-12 floors were completed - 95%;
  • The floor screed on the 8th and 9th floors was completed - 100%;
  • 40% of SPOK stained glass systems (input group) have been completed;
  • 85% of window structures from the 5th to the 15th floor have been installed;
  • 95% of SPOK stained glass systems from the 1st to the 4th floor have been installed;
  • 95% of the double-glazed windows of the stained-glass systems from the 1st to the 4th floor have been installed;
  • 52% of the cladding of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine");
  • Work on 100% of external networks (water supply) was completed;
  • The installation of the hinged ventilated facade from the 5th to the 33rd floor was completed - 54%;
  • 75% of SPOK stained glass systems from the 15th to the 33rd floor have been installed.