A136 Highlight Tower construction progress for October:

  • Bricklaying of walls and partitions from the -2nd to the 33rd floor has been completed - 95%, and the masonry of utility network niches from the 26th to the 33rd floor is also being done;
  • The brickwork of the roof was completed at the marks 110.300 and 113.200 in the volume: 235 m3 - 100%;
  • Plumbing connections of apartments from the 7th to the 32nd floor have been laid out - 90%, work is being done on the 6th and 33rd floors;
  • Screeding of floors 8-28 has been completed - 100%, screeding is currently being done on floors 29-30;
  • The plastering of the walls of the MZK from the 7th to the 17th floors has been completed - 100%, and the plastering of the walls on the 19th, 21st, and 22nd floors is currently underway;
  • Plumbing works from -2 to 34 floors have been completed - 80%, K1 installation works are currently being carried out on floors 30-33;
  • Electrical installation works from -2 to 24 floors have been completed - 90%, work is currently being carried out on floors 24-27;
  • The smoke removal system in axes 1-22/А-М in the parking lot on the -2nd and -1st floors has been implemented - 50%;
  • The ventilation system (galvanized air duct boxes) in axes 1-22/А-М -2 and -1 floor - 60%;
  • An automatic fire extinguishing system (splinker fire extinguishing system) was implemented in axes: 7-16 E-Y from -2 to 10 floors - 90%;
  • Plastering of the brick walls of the technical premises and MZK -2 and -1 floors was completed - 45%;
  • 95% of stained glass systems of SPOK (input group) in axes 13-17 /В-Ж with odm: 0.000 to 14.630 have been completed;
  • Mounted window structures from the 1st to the 31st floor in axes: 1-22/А-М -95%;
  • Double-glazed units of window structures from the 1st to the 31st floor have been installed in axes: 1-22/А-М -95%;
  • SPOK stained glass systems were installed from the 1st to the 31st floor, in axes: 1-22/А-М -97%;
  • Double-glazed units of stained-glass systems were installed from the 1st to the 31st floor, in the axes: 1-22/А-М -97%;
  • The roof is arranged on the stylobate: 2nd floor in axes 15-22/ Ж-Х on odm: + 4.160, 3rd floor in axes 8-13/А*-В on odm. 7.620, 5th floor in axes 7-12/А-В and in axes 15-22/Ж-П on dept. 14,630 – 80%;
  • Cladding of the facade of the stylobate is arranged (insulation, subsystem installation of decorative stone "Travertine") -80%;
  • Completed work on the insertion of external networks (water pipeline) - 100%;
  • Completed work on the insertion of external networks (sewage) - 100%;
  • Installation of the hinged ventilated facade from the 5th to the 33rd floor in axes 1-22 /А-М - 92%;
  • Preparatory work on lighting the facade of the stylobate (installation of external lighting electrical networks) 1-5 floor in axes 1-22 /А - Р - 90% has been completed;
  • Preparatory work on lighting the facade of the building (installation of external lighting electrical networks) has been completed - 90%;
  • Installation of passenger elevators of the commercial part - 100%;
  • Installation of freight elevators - 5%;
  • Installation of low-current systems (electrical wiring of low-current networks) from 1 to 30 - 95%;
  • The roof of the building in the axes 1-22/А-М at the marks 110.300 and 113.200 is arranged - 100%.