Construction progress for October 2024
11.11.2024
Go back
A136 Highlight Tower construction progress for October:
- Bricklaying of walls and partitions from the -2nd to the 33rd floor has been completed - 95%, and the masonry of utility network niches from the 26th to the 33rd floor is also being done;
- The brickwork of the roof was completed at the marks 110.300 and 113.200 in the volume: 235 m3 - 100%;
- Plumbing connections of apartments from the 7th to the 32nd floor have been laid out - 90%, work is being done on the 6th and 33rd floors;
- Screeding of floors 8-28 has been completed - 100%, screeding is currently being done on floors 29-30;
- The plastering of the walls of the MZK from the 7th to the 17th floors has been completed - 100%, and the plastering of the walls on the 19th, 21st, and 22nd floors is currently underway;
- Plumbing works from -2 to 34 floors have been completed - 80%, K1 installation works are currently being carried out on floors 30-33;
- Electrical installation works from -2 to 24 floors have been completed - 90%, work is currently being carried out on floors 24-27;
- The smoke removal system in axes 1-22/А-М in the parking lot on the -2nd and -1st floors has been implemented - 50%;
- The ventilation system (galvanized air duct boxes) in axes 1-22/А-М -2 and -1 floor - 60%;
- An automatic fire extinguishing system (splinker fire extinguishing system) was implemented in axes: 7-16 E-Y from -2 to 10 floors - 90%;
- Plastering of the brick walls of the technical premises and MZK -2 and -1 floors was completed - 45%;
- 95% of stained glass systems of SPOK (input group) in axes 13-17 /В-Ж with odm: 0.000 to 14.630 have been completed;
- Mounted window structures from the 1st to the 31st floor in axes: 1-22/А-М -95%;
- Double-glazed units of window structures from the 1st to the 31st floor have been installed in axes: 1-22/А-М -95%;
- SPOK stained glass systems were installed from the 1st to the 31st floor, in axes: 1-22/А-М -97%;
- Double-glazed units of stained-glass systems were installed from the 1st to the 31st floor, in the axes: 1-22/А-М -97%;
- The roof is arranged on the stylobate: 2nd floor in axes 15-22/ Ж-Х on odm: + 4.160, 3rd floor in axes 8-13/А*-В on odm. 7.620, 5th floor in axes 7-12/А-В and in axes 15-22/Ж-П on dept. 14,630 – 80%;
- Cladding of the facade of the stylobate is arranged (insulation, subsystem installation of decorative stone "Travertine") -80%;
- Completed work on the insertion of external networks (water pipeline) - 100%;
- Completed work on the insertion of external networks (sewage) - 100%;
- Installation of the hinged ventilated facade from the 5th to the 33rd floor in axes 1-22 /А-М - 92%;
- Preparatory work on lighting the facade of the stylobate (installation of external lighting electrical networks) 1-5 floor in axes 1-22 /А - Р - 90% has been completed;
- Preparatory work on lighting the facade of the building (installation of external lighting electrical networks) has been completed - 90%;
- Installation of passenger elevators of the commercial part - 100%;
- Installation of freight elevators - 5%;
- Installation of low-current systems (electrical wiring of low-current networks) from 1 to 30 - 95%;
- The roof of the building in the axes 1-22/А-М at the marks 110.300 and 113.200 is arranged - 100%.