A136 Highlight Tower
Construction progress for July 2024

30.07.2024

Go back

The following works were performed at the A136 Highlight Tower construction site in July:

  • Arrangement of screed floors 10-13 floor;
  • Installation of SPOK stained glass systems from the 31st to the 33rd floor;
  • Installation of subsystems and cladding of the stylobate with natural stone;
  • Installation of electrical lighting systems for the facade of the stylobate;
  • Installation of electric lighting systems of the facade of the high part;
  • Installation of a hinged ventilated facade from the 6th to the 32nd floor;
  • Installation of work on the arrangement of electrical networks of the house;
  • Installation of low current systems;
  • Installation works on the installation of water supply and sewerage;
  • Installation of heating pipelines for apartments on the 18th-21st floor;
  • Installation of water supply pipelines for apartments on the 18th-31st floor;
  • Installation work on the installation of fire water mains;
  • Installation of parking lot ventilation -2nd and -1st floor;
  • Installation of freight elevators has begun;
  • Arrangement of the stylobate roof;
  • Preparatory work on landscaping.