Construction progress for July 2024
30.07.2024
Go back
The following works were performed at the A136 Highlight Tower construction site in July:
- Arrangement of screed floors 10-13 floor;
- Installation of SPOK stained glass systems from the 31st to the 33rd floor;
- Installation of subsystems and cladding of the stylobate with natural stone;
- Installation of electrical lighting systems for the facade of the stylobate;
- Installation of electric lighting systems of the facade of the high part;
- Installation of a hinged ventilated facade from the 6th to the 32nd floor;
- Installation of work on the arrangement of electrical networks of the house;
- Installation of low current systems;
- Installation works on the installation of water supply and sewerage;
- Installation of heating pipelines for apartments on the 18th-21st floor;
- Installation of water supply pipelines for apartments on the 18th-31st floor;
- Installation work on the installation of fire water mains;
- Installation of parking lot ventilation -2nd and -1st floor;
- Installation of freight elevators has begun;
- Arrangement of the stylobate roof;
- Preparatory work on landscaping.