Construction progress for February 2024
20.02.2024
Go back
A136 Highlight Tower by DIM is being built at a fast pace!
We share the latest news from the construction site for February:
- Brickwork from the 24th to the 34th floor has been completed - 80%.
- The brickwork of the roof is completed - 100%.
- 85% of the window structures from the 15th to the 34th floor have been installed.
- 80% of double-glazed units of window structures from the 15th to the 34th floor have been installed.
- 71% of SPOK stained glass systems from the 15th to the 34th floor have been installed.
- 59% of double-glazed units of stained glass systems from the 15th to the 34th floor have been installed.
- The roof is arranged on the stylobate of 2, 3, 4, 5 floors - 50%.
- 42% of the cladding of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine").
- Work on 75% of external networks (sewage) has been completed.
- The installation of the hinged ventilated facade from the 5th to the 34th floor has been completed - 47%.
- Preparatory work on lighting the facade of the building has been completed - 42%.
- The roof of the house is 100% fixed.