A136 Highlight Tower
Construction progress for February 2024

20.02.2024

Go back

A136 Highlight Tower by DIM is being built at a fast pace!

We share the latest news from the construction site for February:

  • Brickwork from the 24th to the 34th floor has been completed - 80%.
  • The brickwork of the roof is completed - 100%.
  • 85% of the window structures from the 15th to the 34th floor have been installed.
  • 80% of double-glazed units of window structures from the 15th to the 34th floor have been installed.
  • 71% of SPOK stained glass systems from the 15th to the 34th floor have been installed.
  • 59% of double-glazed units of stained glass systems from the 15th to the 34th floor have been installed.
  • The roof is arranged on the stylobate of 2, 3, 4, 5 floors - 50%.
  • 42% of the cladding of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine").
  • Work on 75% of external networks (sewage) has been completed.
  • The installation of the hinged ventilated facade from the 5th to the 34th floor has been completed - 47%.
  • Preparatory work on lighting the facade of the building has been completed - 42%.
  • The roof of the house is 100% fixed.