Construction progress for January 2024
29.01.2024
Go back
A136 Highlight Tower by DIM is being built at a fast pace!
We share the latest news from the construction site for January:
- Brickwork from -2 to 24th floor has been completed - 95%.
- Brickwork from the 24th to the 34th floor has been completed - 70%.
- Bricklaying of the roof has been completed - 95%.
- Plumbing works from -2nd to 34th floor have been completed - 70%.
- The horizontal heating system on the 8th and 9th floors has been completed - 95%.
- 75% of the window structures from the 15th to the 34th floor have been installed.
- 69% of double-glazed units of window structures from the 15th to the 34th floor have been installed.
- 70% of SPOK stained glass systems from the 15th to the 34th floor have been installed.
- 57% of double-glazed windows of stained glass systems from the 15th to the 34th floor have been installed.
- Work on 67% of external networks (sewage) was completed.
- The installation of the hinged ventilated facade from the 5th to the 34th floor has been completed - 40%.
- Preparatory work on lighting the facade of the building has been completed - 35%.
- The roof of the house is installed - 75%.