A136 Highlight Tower by DIM is being built at a fast pace!

We share the latest news from the construction site for January:

  • Brickwork from -2 to 24th floor has been completed - 95%.
  • Brickwork from the 24th to the 34th floor has been completed - 70%.
  • Bricklaying of the roof has been completed - 95%.
  • Plumbing works from -2nd to 34th floor have been completed - 70%.
  • The horizontal heating system on the 8th and 9th floors has been completed - 95%.
  • 75% of the window structures from the 15th to the 34th floor have been installed.
  • 69% of double-glazed units of window structures from the 15th to the 34th floor have been installed.
  • 70% of SPOK stained glass systems from the 15th to the 34th floor have been installed.
  • 57% of double-glazed windows of stained glass systems from the 15th to the 34th floor have been installed.
  • Work on 67% of external networks (sewage) was completed.
  • The installation of the hinged ventilated facade from the 5th to the 34th floor has been completed - 40%.
  • Preparatory work on lighting the facade of the building has been completed - 35%.
  • The roof of the house is installed - 75%.