Construction progress for June 2024
30.06.2024
Go back
The following works were performed at the A136 Highlight Tower construction site in June:
- Laying of internal floor communications (heating, water supply) - 5,000 sq.m
- Complex of works on installation of hinged ventilated facade - 540 m2
- Brickwork of external and internal walls was completed - 116 m3
- The brickwork of the partitions of the apartments was completed - 839 m2
- Finished facing works with natural stone "Travertine" - 82 m2
- Installation of Travertine stone, insulation and subsystems - 700 m2
- Glazing of the input group completed - 100%
- Installation of facade elements from Emolite - 40 m2
- Installation of NVF insulation - 670 m2
- Installation of the NVF subsystem - 510 m2
- Installation of decorative facade elements - 530 m2
- Installation of NVF ceramic granite - 310 m2
- Installation of SPOK frames - 1373 m2
- Installation of double-glazed windows - 547 m2
- Installation of window structures - 575 m2
- Installation of the transparent structure of the lobby - 145 m2
- Installation of steel pipelines for water supply and drainage - 600 m
- Installation of cable lines in corrugated pipes for facade lighting - 1,500 square meters
- Installation of cable power supply networks for apartments and household consumers in corrugated pipes - 8,900 m.pog
- Installation of supply and exhaust ventilation ducts - 160 m2