A136 Highlight Tower
Construction progress for June 2024

30.06.2024

Go back

The following works were performed at the A136 Highlight Tower construction site in June:

  • Laying of internal floor communications (heating, water supply) - 5,000 sq.m
  • Complex of works on installation of hinged ventilated facade - 540 m2
  • Brickwork of external and internal walls was completed - 116 m3
  • The brickwork of the partitions of the apartments was completed - 839 m2
  • Finished facing works with natural stone "Travertine" - 82 m2
  • Installation of Travertine stone, insulation and subsystems - 700 m2
  • Glazing of the input group completed - 100%
  • Installation of facade elements from Emolite - 40 m2
  • Installation of NVF insulation - 670 m2
  • Installation of the NVF subsystem - 510 m2
  • Installation of decorative facade elements - 530 m2
  • Installation of NVF ceramic granite - 310 m2
  • Installation of SPOK frames - 1373 m2
  • Installation of double-glazed windows - 547 m2
  • Installation of window structures - 575 m2
  • Installation of the transparent structure of the lobby - 145 m2
  • Installation of steel pipelines for water supply and drainage - 600 m
  • Installation of cable lines in corrugated pipes for facade lighting - 1,500 square meters
  • Installation of cable power supply networks for apartments and household consumers in corrugated pipes - 8,900 m.pog
  • Installation of supply and exhaust ventilation ducts - 160 m2