Construction progress for March 2024
31.03.2024
Go back
A136 Highlight Tower by DIM is being built at a fast pace!
We share the latest news from the construction site for March:
- Brickwork from the 24th to the 34th floor has been completed - 90%;
- Completed electrical installation work from -2 to 27th floor - 48%;
- 100% of double-glazed windows of window structures from the 15th to the 34th floor have been installed;
- 95% of window structures from the 15th to the 34th floor have been installed;
- 72% of SPOK stained glass systems from the 15th to the 34th floor have been installed;
- 2, 3, 4, 5 floors are covered with a stylobate roof - 55%;
- 45% of the facing of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine");
- Work on 80% of external networks (sewage) was completed;
- The installation of the hinged ventilated facade from the 5th to the 34th floor was completed - 51%;
- Preparatory work on lighting the facade of the building has been completed - 45%;
- Installation of passenger elevators of the commercial part - 100%.