A136 Highlight Tower
Construction progress for March 2024

31.03.2024

Go back

A136 Highlight Tower by DIM is being built at a fast pace!

We share the latest news from the construction site for March:

  • Brickwork from the 24th to the 34th floor has been completed - 90%;
  • Completed electrical installation work from -2 to 27th floor - 48%;
  • 100% of double-glazed windows of window structures from the 15th to the 34th floor have been installed;
  • 95% of window structures from the 15th to the 34th floor have been installed;
  • 72% of SPOK stained glass systems from the 15th to the 34th floor have been installed;
  • 2, 3, 4, 5 floors are covered with a stylobate roof - 55%;
  • 45% of the facing of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine");
  • Work on 80% of external networks (sewage) was completed;
  • The installation of the hinged ventilated facade from the 5th to the 34th floor was completed - 51%;
  • Preparatory work on lighting the facade of the building has been completed - 45%;
  • Installation of passenger elevators of the commercial part - 100%.