Construction progress for May 2024
28.05.2024
Go back
The following works were performed at the A136 Highlight Tower construction site in May:
- Brickwork from the 24th to the 33rd floor has been completed - 95%;
- Completed electrical installation work from -2 to 34th floor - 37%;
- The smoke removal system of floors -2 and -1 was completed - 50%;
- The ventilation system of floors -2 and -1 was completed - 48%;
- The automatic fire extinguishing system was implemented from -2 to 5 floors - 70%;
- 90% of stained glass systems of SPOK (input group) have been completed;
- 57% of the facing of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine");
- Work on 90% of external networks (sewage) was completed;
- The installation of the hinged ventilated facade from the 5th to the 33rd floor has been completed - 65%;
- Preparatory work on lighting the facade of the stylobate on the 1st-5th floor has been completed - 60%;
- Preparatory work on lighting the facade of the building has been completed - 50%.