A136 Highlight Tower
Construction progress for May 2024

28.05.2024

Go back

The following works were performed at the A136 Highlight Tower construction site in May:

  • Brickwork from the 24th to the 33rd floor has been completed - 95%;
  • Completed electrical installation work from -2 to 34th floor - 37%;
  • The smoke removal system of floors -2 and -1 was completed - 50%;
  • The ventilation system of floors -2 and -1 was completed - 48%;
  • The automatic fire extinguishing system was implemented from -2 to 5 floors - 70%;
  • 90% of stained glass systems of SPOK (input group) have been completed;
  • 57% of the facing of the stylobate facade has been arranged (insulation, subsystem installation of decorative stone "Travertine");
  • Work on 90% of external networks (sewage) was completed;
  • The installation of the hinged ventilated facade from the 5th to the 33rd floor has been completed - 65%;
  • Preparatory work on lighting the facade of the stylobate on the 1st-5th floor has been completed - 60%;
  • Preparatory work on lighting the facade of the building has been completed - 50%.