Construction progress for August 2025
03.09.2025
Go back
Construction progress of A136 Highlight Tower for August 2025:
- Plastering of brick walls in technical rooms and MCP -2 and -1 floors is 95% complete.
- Works continue on finishing coating, decoration of MCP walls with decorative plaster (marble) on floors 8, 12, 16-19, 25-28, 31-33.
- Installation of suspended ceilings (cube-rail) from the 6th to the 33rd floor is 40% complete.
- Smoke removal system in the parking lot (axes 1-22/A-M, -2, and -1 floors) is 80% complete. Fans are currently being installed on the roof.
- Installation of ventilated facade at the entrance to the parking lot is 90% complete.
- Installation of stairway fences is 100% complete.
- Installation of residential elevator lifts is 40% complete.
- Installation of entrance doors on the 33rd floor.
- Installation of doors in technical rooms of MCP and fire doors in vestibules of staircases from the 6th to the 33rd floor, as well as in the parking lot is 100% complete.
- Waterproofing of the parking lot is 70% complete.
- Sand preparation for landscaping is 90% complete.
- Gravel preparation for landscaping is 70% complete.
Monolithic construction of stairs and central entrance group wings is complete.
Wet facade installation on the roof is 50% complete.