Construction progress for October 2025
05.11.2025
Go back
Construction progress of A136 Highlight Tower for October 2025:
- Continuation of finishing works, decoration of walls with decorative plaster (marble) on floors 8, 17, 27, 31-33.
- Installation of suspended ceilings (cubicle) from floors 6 to 33 – 80% completed.
- Installation of ceramic tiles on stair landings – 50% completed.
- Continuation of works on the roof: installation of fans and galvanized ducts for smoke extraction system.
- Installation of ventilated facade at the entrance to the parking – 95% completed.
- Installation of residential passenger elevators – door installation and commissioning works.
- Waterproofing works in the parking area – 90% completed.
- Gravel preparation for landscaping – 80% completed.
- Installation of 'wet' facade on the roof – 90% completed.
- Installation of granite paving for the central entrance group – 50% completed.
- Continuation of decoration works in the lobby of the residential part (1st floor).
- Decoration of parking walls (laying ceramic tile floors).
- Painting of walls on stair landings from 1st to 33rd floor.
- Installation of entrance doors on the 5th floor.
- Installation works for the irrigation system.
- Installation of pumping water supply equipment in the building.
- Installation of lightning protection on the roof.
- Installation of fire gates and curtains at the parking entrance.
- Installation of equipment in the electrical room.