A136 Highlight Tower
Construction progress for October 2025

05.11.2025

Go back

Construction progress of A136 Highlight Tower for October 2025:

  • Continuation of finishing works, decoration of walls with decorative plaster (marble) on floors 8, 17, 27, 31-33.
  • Installation of suspended ceilings (cubicle) from floors 6 to 33 – 80% completed.
  • Installation of ceramic tiles on stair landings – 50% completed.
  • Continuation of works on the roof: installation of fans and galvanized ducts for smoke extraction system.
  • Installation of ventilated facade at the entrance to the parking – 95% completed.
  • Installation of residential passenger elevators – door installation and commissioning works.
  • Waterproofing works in the parking area – 90% completed.
  • Gravel preparation for landscaping – 80% completed.
  • Installation of 'wet' facade on the roof – 90% completed.
  • Installation of granite paving for the central entrance group – 50% completed.
  • Continuation of decoration works in the lobby of the residential part (1st floor).
  • Decoration of parking walls (laying ceramic tile floors).
  • Painting of walls on stair landings from 1st to 33rd floor.
  • Installation of entrance doors on the 5th floor.
  • Installation works for the irrigation system.
  • Installation of pumping water supply equipment in the building.
  • Installation of lightning protection on the roof.
  • Installation of fire gates and curtains at the parking entrance.
  • Installation of equipment in the electrical room.