A136 Highlight Tower
Construction progress for November 2025

09.12.2025

Go back

Construction progress of A136 Highlight Tower for November 2025:

  • Works on finishing coating and decoration of walls with decorative stucco (marble) on the 5th and 33rd floors are continuing.
  • Installation of ceramic tiles on stair landings - 52%, and in the parking area - 70%.
  • Lobby decoration (wall stucco, wall and floor decoration with ceramic tiles) - 90%, currently working on wall decoration with veneer.
  • Installation of ventilated facade on entrance group of 1-5 floors - 99%.
  • Installation of passenger elevators (commissioning works in progress) - 95%.
  • Installation of ventilation shaft grilles on the roof - 80%.
  • Lightning protection works completed - 100%.
  • Parking hydro insulation - 95%.
  • Sand preparation for landscaping - 90%.
  • Gravel preparation for landscaping - 80%.
  • Construction of monolithic stair and vestibule structures in central entrance group.
  • Works on wet facade installation on the roof completed - 100%.
  • Granite pavement installation at central entrance - 80%.
  • Works on Technical Premises decoration completed, equipment installation in progress.
  • Installation of ventilated facade at parking entrance.
  • Continuing installation of smoke extraction systems on technical floor and roof.
  • Continuing installation of automatic irrigation system and external lighting.
  • Decoration of walls, ceilings and floors of staircases.
  • Concrete flooring installation in the parking area.