Construction progress for November 2025
09.12.2025
Go back
Construction progress of A136 Highlight Tower for November 2025:
- Works on finishing coating and decoration of walls with decorative stucco (marble) on the 5th and 33rd floors are continuing.
- Installation of ceramic tiles on stair landings - 52%, and in the parking area - 70%.
- Lobby decoration (wall stucco, wall and floor decoration with ceramic tiles) - 90%, currently working on wall decoration with veneer.
- Installation of ventilated facade on entrance group of 1-5 floors - 99%.
- Installation of passenger elevators (commissioning works in progress) - 95%.
- Installation of ventilation shaft grilles on the roof - 80%.
- Lightning protection works completed - 100%.
- Parking hydro insulation - 95%.
- Sand preparation for landscaping - 90%.
- Gravel preparation for landscaping - 80%.
- Construction of monolithic stair and vestibule structures in central entrance group.
- Works on wet facade installation on the roof completed - 100%.
- Granite pavement installation at central entrance - 80%.
- Works on Technical Premises decoration completed, equipment installation in progress.
- Installation of ventilated facade at parking entrance.
- Continuing installation of smoke extraction systems on technical floor and roof.
- Continuing installation of automatic irrigation system and external lighting.
- Decoration of walls, ceilings and floors of staircases.
- Concrete flooring installation in the parking area.