Construction progress for December 2025

05.01.2026

Go back

Construction progress of A136 Highlight Tower for December 2025:

  • Work continues on finishing the decorative plaster (marble) on the walls of the MEP on the 5th and 33rd floors.
  • Installation of suspended ceilings (cube-rail) from 6 to 33 floors - 90%.
  • Installation of ceramic tiles on stair landings - 55%, and in the MEP parking lot - 80%.
  • Decoration of the lobby (wall plastering, wall and floor decoration with ceramic tiles) - 92%, work on wall decoration with veneer continues.
  • Parking floor installation - 90%.
  • Work continues on installing fans and galvanized smoke exhaust boxes on the roof.
  • Low-current systems installation from 1 to 33 floors - 97%.
  • Finishing work on cladding with natural stone (Travertine) of the 2nd stylobate.
  • Installation of ventilated facade at the entrance to the parking lot - 95%.
  • Equipment installation work in the technical room.
  • Installation of passenger elevators (commissioning work) - 96%.
  • Installation of ventilation shaft grilles on the roof - 90%.
  • Parking waterproofing - 100%.
  • Installation of gravel preparation for landscaping - 90%.
  • Installation of monolithic structures of stairs and vestibules of the central entrance group.
  • Installation of granite paving at the central entrance - 90%.
  • Continued installation of automatic watering system and external lighting.
  • Continued wall, ceiling, and floor decoration of staircases.
  • Installation of wheel stoppers and marking in the parking lot.
  • Landscaping works are carried out.