Construction progress for June 2025
30.06.2025
Go back
Construction progress of A136 Highlight Tower for June 2025:
- The floor screed on the 33rd floor has been completed - 100%.
- The plastering of the walls of the technical floor on the 33rd floor has been completed - 100%, plastering works on the 32nd floor are currently in progress.
- Finishing decorative plaster 'marble' is being applied on the 9th, 12th, 13th, and 14th floors.
- The installation of suspended ceilings (cub-rail) on the 6th-31st floors is in progress.
- Equipment installation works for the cold water supply pump room are ongoing.
- Smoke extraction system installation on axes 1-22 / A-M of the parking lot on the -2nd and -1st floors - 60%.
- Ventilated facade installation at the entrance to the parking lot - 70%.
- Installation of passenger lifts in the residential part - 35%.
- Decoration of the lobby of the residential part (1st floor).
- Installation of entrance doors on the 32nd-33rd floors and technical doors in the parking lot is in progress.
- Preparatory work for landscaping of the territory has begun.
- Work is underway to install lighting in the technical floor: connection of LED strip and linear luminaires.