A136 Highlight Tower
Construction progress for April 2026

30.04.2026

Go back

Construction progress of A136 Highlight Tower for April 2026:

  • Installation of pump equipment for hot water supply and cold water supply – 100%.
  • Installation of ceramic tiles on stair landings – 100%.
  • Wall finishing with veneer in the lobby – 100%.
  • Installation of parking floors with markings and navigation – 99% (work continues on polymer coating of the ramp).
  • Installation of suspended ceiling with cube rails in the MZK continues.
  • Installation of sand and gravel foundation for landscaping – 100%.
  • Installation of wet roof facade – 100%.
  • Installation of granite paving at the central entrance – 95% (work continues on paving in the inner courtyard and along School No. 37).
  • Finishing of the transformer room and installation of equipment – completed.
  • The cladding of the 2nd stylobate with natural stone (Travertine) continues.
  • Installation of ventilated facade at the parking entrance – ongoing.
  • Installation of smoke exhaust systems for the technical floor and roof.
  • Installation of the automatic irrigation system and external lighting – ongoing.
  • Installation of decorative plaster (Marmerin) on the 5th floor of MZK.
  • Landscaping of the adjacent territory continues.
  • Installation of terrace fences.
  • Works on the children's playground have started.
  • Installation of external lighting for landscaping.
  • Installation of stormwater drainage grates with connection to the parking entrance.