Construction progress for April 2026
30.04.2026
Go back
Construction progress of A136 Highlight Tower for April 2026:
- Installation of pump equipment for hot water supply and cold water supply – 100%.
- Installation of ceramic tiles on stair landings – 100%.
- Wall finishing with veneer in the lobby – 100%.
- Installation of parking floors with markings and navigation – 99% (work continues on polymer coating of the ramp).
- Installation of suspended ceiling with cube rails in the MZK continues.
- Installation of sand and gravel foundation for landscaping – 100%.
- Installation of wet roof facade – 100%.
- Installation of granite paving at the central entrance – 95% (work continues on paving in the inner courtyard and along School No. 37).
- Finishing of the transformer room and installation of equipment – completed.
- The cladding of the 2nd stylobate with natural stone (Travertine) continues.
- Installation of ventilated facade at the parking entrance – ongoing.
- Installation of smoke exhaust systems for the technical floor and roof.
- Installation of the automatic irrigation system and external lighting – ongoing.
- Installation of decorative plaster (Marmerin) on the 5th floor of MZK.
- Landscaping of the adjacent territory continues.
- Installation of terrace fences.
- Works on the children's playground have started.
- Installation of external lighting for landscaping.
- Installation of stormwater drainage grates with connection to the parking entrance.