Construction progress for March 2026
02.04.2026
Go back
Construction progress of A136 Highlight Tower for March 2026:
- Installation of suspended ceilings (cub-rail) from the 6th to the 33rd floor — 96%.
- Installation of ceramic tiles on stair platforms — 90%, and MZK parking — 100%.
- Works continue on wall cladding with veneer in the lobby.
- Works are being carried out for finishing floor coverings and marking application in the parking lot.
- Installation of suspended ventilated facade at the parking entrance.
- Works are ongoing for terrace fencing.
- Continuation of commissioning works for passenger elevators in the residential section.
- Installation works for setting up automatic irrigation system and external lighting.
- Continuation of equipment installation works in the transformer substation.
- Painting of parking walls.
- Continuation of monolithic structure installation works for stairs and entrance hall of the central entrance group.
- Installation of granite pavement at the central entrance.
- Continuation of installation of wheel stoppers and marking in the parking lot.
- Landscaping works in progress.
- Installation of lighting in the residential section of MZK.