A136 Highlight Tower
Construction progress for March 2026

02.04.2026

Go back

Construction progress of A136 Highlight Tower for March 2026:

  • Installation of suspended ceilings (cub-rail) from the 6th to the 33rd floor — 96%.
  • Installation of ceramic tiles on stair platforms — 90%, and MZK parking — 100%.
  • Works continue on wall cladding with veneer in the lobby.
  • Works are being carried out for finishing floor coverings and marking application in the parking lot.
  • Installation of suspended ventilated facade at the parking entrance.
  • Works are ongoing for terrace fencing.
  • Continuation of commissioning works for passenger elevators in the residential section.
  • Installation works for setting up automatic irrigation system and external lighting.
  • Continuation of equipment installation works in the transformer substation.
  • Painting of parking walls.
  • Continuation of monolithic structure installation works for stairs and entrance hall of the central entrance group.
  • Installation of granite pavement at the central entrance.
  • Continuation of installation of wheel stoppers and marking in the parking lot.
  • Landscaping works in progress.
  • Installation of lighting in the residential section of MZK.