Construction progress in February 2026
03.03.2026
Go back
Construction progress of A136 Highlight Tower in February 2026:
- Decoration of the underground parking (puttying and painting walls, installation of suspended ceiling).
- Painting walls and laying ceramic tiles on staircases of residential part from 1st to 33rd floor.
- Facing with natural stone (Travertine) of the 2nd stylobate.
- Installation of ventilated facade at the entrance to the parking lot.
- Installation of smoke extraction system for technical floor and roof.
- Continuation of decoration works in the lobby of the residential part (1st floor).
- Commissioning works for passenger elevators in the residential part.
- Landscaping of the territory (granite paving).
- Installation works of automatic watering system and external lighting.
- Finishing works of decoration walls of the underground parking with decorative plaster (marble) on the 5th floor.
- Installation of lighting in the underground parking (connection of LED strips and linear fixtures, wall sconces).
- Installation of fire curtains at the entrance to the parking lot.
- Equipment installation in the transformer room.
- Decoration of walls in the lobby of the 1st floor with veneer.
- Finishing of concrete floors in the parking lot.
- Painting walls and ceiling of the parking lot.
- Continuation of installation of wheel stoppers and marking.
- Landscaping work in the area improvement.