A136 Highlight Tower
Construction progress in February 2026

03.03.2026

Go back

Construction progress of A136 Highlight Tower in February 2026:

  • Decoration of the underground parking (puttying and painting walls, installation of suspended ceiling).
  • Painting walls and laying ceramic tiles on staircases of residential part from 1st to 33rd floor.
  • Facing with natural stone (Travertine) of the 2nd stylobate.
  • Installation of ventilated facade at the entrance to the parking lot.
  • Installation of smoke extraction system for technical floor and roof.
  • Continuation of decoration works in the lobby of the residential part (1st floor).
  • Commissioning works for passenger elevators in the residential part.
  • Landscaping of the territory (granite paving).
  • Installation works of automatic watering system and external lighting.
  • Finishing works of decoration walls of the underground parking with decorative plaster (marble) on the 5th floor.
  • Installation of lighting in the underground parking (connection of LED strips and linear fixtures, wall sconces).
  • Installation of fire curtains at the entrance to the parking lot.
  • Equipment installation in the transformer room.
  • Decoration of walls in the lobby of the 1st floor with veneer.
  • Finishing of concrete floors in the parking lot.
  • Painting walls and ceiling of the parking lot.
  • Continuation of installation of wheel stoppers and marking.
  • Landscaping work in the area improvement.