Construction progress for January 2026
30.01.2026
Go back
Construction progress of A136 Highlight Tower for January 2026:
- Finishing works continue, walls decoration with decorative plaster (marble) on the 5th and 33rd floors.
- Installation of suspended ceilings (cube-rail) from the 6th to the 33rd floor - 95%.
- Installation of ceramic tiles on stair landings - 57%, and on the garage - 90%.
- Lobby decoration (wall plastering, wall and floor decoration with ceramic tiles) - 100%, wall decoration with veneer in progress.
- Parking floor installation - 95%.
- Equipment installation in the transformer substation continues.
- Installation of passenger elevators (commissioning works) - 97%.
- Installation of ventilation shaft grilles on the roof - 92%.
- Installation of gravel and sand preparation for landscaping - 93%.
- Continuation of the installation of monolithic structures for stairs and central entrance wings.
- Installation of granite paving for the central entrance - 92%.
- Continuation of installation of wheel stops and marking in the parking lot.
- Landscaping works are in progress.