Construction progress for April 2023

05.05.2023

Go back

We report fresh news on the construction of the eco-city LUCKY LAND by DIM! We are preparing the 3rd house to receive the certificate of readiness. We continue to build the 4th and 5th houses.

Report for April on the construction of the best eco-city LUCKY LAND:

Building No. 3, Section 1:

  • work on the installation of external ETR networks is being carried out;
  • arrangement of equipment of basement premises;
  • equipment of the entrance group;
  • arrangement of entrance group porches;
  • installation of pumping equipment and water metering unit;
  • equipping common areas, stairwells;
  • arrangement of ventilation and smoke removal systems;
  • installation of fire alarm systems;
  • installation of a fire splinker fire extinguishing pumping station;
  • installation of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • arrangement of ceramic tiles in MZK.

Building No. 3, Section 2:

  • arrangement of equipment of basement premises;
  • arrangement of ventilation and smoke removal systems;
  • installation of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • equipping common areas, stairwells;
  • installation of ceramic tiles in the MZK, stairwells.

Building No. 3, Section 3:

  • arrangement of equipment of basement premises;
  • equipping common areas;
  • arrangement of ventilation and smoke removal systems;
  • installation of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • arrangement of equipment of public places;
  • installation of ceramic tiles in the MZK, stairwells;
  • maintenance works at the entrance to the parking lot.

Improvement of Railway Station No. 3:

  • preparation of the base of the soil for the performance of works on the improvement of section 1 - the outer yard.

Building No. 4, Section 1:

  • installation of sound insulation under the floor screed from the 1st to the 5th floor;
  • performance of facade insulation works.

Building No. 4, Section 2:

  • performance of facade insulation works;
  • installation of guides for elevators.

Building No. 4, Section 3:

  • arrangement of facades;
  • installation preparatory work for the installation of elevators.

Building No. 6, Section 2:

  • work on the arrangement of brickwork of internal walls and partitions on floors 8-14 is being carried out;
  • arrangement of waterproofing covers of ventilation shafts;
  • installation of smoke exhaust fans on the roof.

Building No. 6, Section 1:

  • installation of a monolithic slab covering above the 14th floor