Construction progress for December 2023

26.12.2023

Go back

LUCKY LAND by DIM is under construction.

We share the latest news from the construction site for December:

Building No. 4, Section 1:

  • installation of K1, K2 risers and air conditioner drainage risers;
  • arrangement of apartment wiring of water supply systems;
  • arrangement of facades;
  • arrangement of risers and apartment wiring of EO systems;
  • work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
  • installation of elevator equipment;
  • installation of waterproofing of terraces on the 3rd and 9th floors.

Building No. 4, Section 2:

  • installation of K1, K2 risers and air conditioner drainage risers;
  • arrangement of facades;
  • work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
  • installation of elevator equipment;
  • installation of waterproofing of terraces on the 3rd and 9th floors.

Building No. 4, Section 3:

  • arrangement of facades;
  • work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
  • installation of elevator equipment;
  • installation of waterproofing of the terraces on the 3rd floor.

Building No. 5, Section 1:

  • arrangement of vertical elements of the 9th floor;
  • arrangement of the floor slab of the 9th floor;
  • installation of ventilation units and staircases.

Building No. 5, Section 2:

  • arrangement of the floor slab of the 9th floor;
  • installation of ventilation units and staircases.

Building No. 5, Section 3, (parking lot):

  • arrangement of monolithic walls, pylons of the underground part;
  • installation of waterproofing and backfilling of the underground part;
  • arrangement of vertical parking elements and waterproofing;
  • arrangement of the parking slab.

Building No. 6, Section 1:

  • installation of technical superstructures on the roof;
  • installation of roof waterproofing;
  • installation of fans of smoke removal systems.

Building No. 6, Section 2:

  • installation of PVC structures on the 13th and 14th floors.