LUCKY LAND by DIM is under construction.

We share a detailed report from the construction site for September:

Building No. 3, Section 1:

  • arrangement of equipment of basement premises;
  • arrangement of equipment input group;
  • arrangement of equipment of public places;
  • arrangement of commissioning works of ventilation and smoke removal systems;
  • arrangement of commissioning works of fire alarm systems;
  • arrangement of commissioning works of the fire fighting splinker fire extinguishing pumping station;
  • arrangement of commissioning works of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • arrangement of decorative plaster in MZK.

Building No. 3, Section 2:

  • arrangement of equipment of basement premises;
  • arrangement of commissioning works of ventilation and smoke removal systems;
  • arrangement of commissioning works of fire alarm systems;
  • installation of equipment in switchboards;
  • arrangement of equipment of public places;
  • arrangement of decorative plaster in MZK;
  • arrangement of equipment input group.

Building No. 3, Section 3:

  • arrangement of equipment of basement premises;
  • arrangement of equipment of public places;
  • installation of ventilation and smoke removal systems (commissioning works);
  • installation of splinker fire extinguishing systems (commissioning works);
  • installation of equipment in switchboards;
  • arrangement of decorative plaster in MZK;
  • arrangement of equipment input group.

Improvement of railroad No. 3:

  • landscaping along house #3.

Building No. 4, Section 1:

  • installation of K1 risers and air conditioner drainage risers;
  • preparatory work on the installation of risers and apartment wiring of power supply systems;
  • arrangement of facades.

Building No. 4, Section 2:

  • arrangement of facades.

Building No. 4, Section 3:

  • arrangement of facades;
  • work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof.

Building No. 4, external networks:

  • arrangement of external networks B1, K1, K2;
  • connection of B1 systems to the city water supply network.

Building No. 5, Section 1:

  • work continues on the installation of the floor slab of the 8th floor.

Building No. 5, Section 2:

  • work continues on the installation of vertical elements of the monolithic frame.

Building No. 5, Section 3:

  • arrangement of the foundation slab.

Building No. 5, parking lot:

  • work continues on the installation of the foundation slab of the parking lot and waterproofing.

House No. 6:

  • connection of B1 systems to the city water supply network.

Building No. 6, Section 1:

  • arrangement of parapets and technical superstructures on the roof;
  • preparatory work for installation of waterproofing on the roof.

Building No. 6, Section 2:

  • work continues on the arrangement of brickwork of internal walls and partitions.