Construction progress for September 2023
05.09.2023
Go back
LUCKY LAND by DIM is under construction.
We share a detailed report from the construction site for September:
Building No. 3, Section 1:
- arrangement of equipment of basement premises;
- arrangement of equipment input group;
- arrangement of equipment of public places;
- arrangement of commissioning works of ventilation and smoke removal systems;
- arrangement of commissioning works of fire alarm systems;
- arrangement of commissioning works of the fire fighting splinker fire extinguishing pumping station;
- arrangement of commissioning works of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- arrangement of decorative plaster in MZK.
Building No. 3, Section 2:
- arrangement of equipment of basement premises;
- arrangement of commissioning works of ventilation and smoke removal systems;
- arrangement of commissioning works of fire alarm systems;
- installation of equipment in switchboards;
- arrangement of equipment of public places;
- arrangement of decorative plaster in MZK;
- arrangement of equipment input group.
Building No. 3, Section 3:
- arrangement of equipment of basement premises;
- arrangement of equipment of public places;
- installation of ventilation and smoke removal systems (commissioning works);
- installation of splinker fire extinguishing systems (commissioning works);
- installation of equipment in switchboards;
- arrangement of decorative plaster in MZK;
- arrangement of equipment input group.
Improvement of railroad No. 3:
- landscaping along house #3.
Building No. 4, Section 1:
- installation of K1 risers and air conditioner drainage risers;
- preparatory work on the installation of risers and apartment wiring of power supply systems;
- arrangement of facades.
Building No. 4, Section 2:
- arrangement of facades.
Building No. 4, Section 3:
- arrangement of facades;
- work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof.
Building No. 4, external networks:
- arrangement of external networks B1, K1, K2;
- connection of B1 systems to the city water supply network.
Building No. 5, Section 1:
- work continues on the installation of the floor slab of the 8th floor.
Building No. 5, Section 2:
- work continues on the installation of vertical elements of the monolithic frame.
Building No. 5, Section 3:
- arrangement of the foundation slab.
Building No. 5, parking lot:
- work continues on the installation of the foundation slab of the parking lot and waterproofing.
House No. 6:
- connection of B1 systems to the city water supply network.
Building No. 6, Section 1:
- arrangement of parapets and technical superstructures on the roof;
- preparatory work for installation of waterproofing on the roof.
Building No. 6, Section 2:
- work continues on the arrangement of brickwork of internal walls and partitions.