Construction progress for October 2023
30.10.2023
Go back
LUCKY LAND by DIM is under construction.
We share the latest news from the construction site for October:
Building No. 3, Section 1:
- arrangement of equipment of basement premises;
- arranging the equipment of the entrance group;
- arrangement of public places;
- arrangement of commissioning works of ventilation and smoke removal systems;
- arrangement of commissioning works of fire alarm systems;
- arrangement of commissioning works of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- arrangement of decorative plaster in MZK.
Building No. 3, Section 2:
- arrangement of equipment of basement premises;
- arrangement of commissioning works of ventilation and smoke removal systems;
- arrangement of commissioning works of fire alarm systems;
- installation of equipment in switchboards;
- arrangement of equipment of public places;
- arrangement of decorative plaster in MZK;
- arrangement of equipment input group.
Building No. 3, Section 3:
- arrangement of equipment of basement premises;
- arrangement of equipment of public places;
- installation of ventilation and smoke removal systems (commissioning works);
- installation of splinker fire extinguishing systems (commissioning works);
- installation of equipment in switchboards;
- arrangement of decorative plaster in MZK;
- arrangement of equipment input group.
Improvement of railroad No. 3:
- landscaping along building No. 3;
- arranging a fence;
- work on landscaping the territory has begun.
Building No. 4, Section 1:
- installation of K1 risers and air conditioner drainage risers;
- arrangement of risers of the internal K1 system;
- arrangement of apartment wiring of water supply systems;
- arrangement of facades;
- arrangement of risers and apartment wiring of EO systems;
- work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof;
- installation of elevator equipment.
Building No. 4, Section 2:
- arrangement of facades;
- work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
- installation of elevator equipment.
Building No. 4, Section 3:
- arrangement of facades;
- work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
- installation of elevator equipment.
Building No. 4, external networks:
- arrangement of external networks B1, K1, K2;
- connection of B1 systems to the city water supply network.
Building No. 5, Section 1:
- arrangement of staircases and ventilation units.
Building No. 5, Section 2:
- arrangement of staircases.
Building No. 5, Section 3:
- arrangement of the foundation slab.
Building No. 5, parking lot:
- work continues on the installation of vertical elements of the parking lot and waterproofing.
House No. 6:
- connection of B1 systems to the city water supply network;
- works are being carried out on the arrangement of brickwork of internal walls and partitions on the 4th-8th floors.
Building No. 6, Section 1:
- installation of technical superstructures on the roof;
- preparatory work for installing waterproofing on the roof.