LUCKY LAND by DIM is under construction.

We share the latest news from the construction site for November:

Building No. 3, Section 1:

  • arrangement of equipment of basement premises;
  • arranging the equipment of the entrance group;
  • arrangement of equipment of public places;
  • arrangement of commissioning works of ventilation and smoke removal systems;
  • arrangement of commissioning works of fire alarm systems;
  • arrangement of commissioning works of splinker fire extinguishing systems;
  • installation of access control systems.

Building No. 3, Section 2:

  • arrangement of equipment of basement premises;
  • arrangement of commissioning works of ventilation and smoke removal systems;
  • arrangement of commissioning works of fire alarm systems;
  • arrangement of equipment of public places;
  • arranging the equipment of the entrance group;
  • installation of access control systems.

Building No. 3, Section 3:

  • arrangement of equipment of basement premises;
  • arrangement of commissioning works of ventilation and smoke removal systems;
  • arrangement of commissioning works of fire alarm systems;
  • arrangement of equipment of public places;
  • arranging the equipment of the entrance group;
  • installation of access control systems.

Improvements, building No. 3:

  • improvement work continues along building No. 3;
  • arranging a fence;
  • landscaping of the territory continues;
  • a rough layer of asphalt concrete covering is laid.

Building No. 4, Section 1:

  • installation of K1, K2 risers and air conditioner drainage risers;
  • arrangement of apartment wiring of water supply systems;
  • arrangement of facades;
  • arrangement of risers and apartment wiring of EO systems;
  • work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof;
  • installation of elevator equipment.

Building No. 4, Section 2:

  • installation of K1, K2 risers and air conditioner drainage risers;
  • arrangement of facades;
  • work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof;
  • installation of elevator equipment.

Building No. 4, Section 3:

  • arrangement of facades;
  • work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof;
  • installation of elevator equipment.

Building No. 4, external networks:

  • arrangement of external networks B1, K1, K2;
  • connection of B1 systems to the city water supply network.

Building No. 5, Section 1:

  • arrangement of vertical elements of the 8th floor;
  • work continues on the installation of the floor slab of the 8th floor;
  • arrangement of vertical elements of the 9th floor;
  • installation of ventilation units and staircases.

Building No. 5, Section 2:

  • arrangement of the floor slab of the 8th floor;
  • arrangement of vertical elements of the 9th floor.

Building No. 5, Section 3:

  • arrangement of monolithic walls, pylons of the underground part.

Building No. 5, parking lot:

  • arrangement of vertical parking elements and waterproofing.

Building No. 6, Section 1:

  • installation of technical superstructures on the roof;
  • installation of roof waterproofing;
  • installation of fans of smoke removal systems.