LUCKY LAND by DIM is under construction.
We share the latest news from the construction site for November:
Building No. 3, Section 1:
- arrangement of equipment of basement premises;
- arranging the equipment of the entrance group;
- arrangement of equipment of public places;
- arrangement of commissioning works of ventilation and smoke removal systems;
- arrangement of commissioning works of fire alarm systems;
- arrangement of commissioning works of splinker fire extinguishing systems;
- installation of access control systems.
Building No. 3, Section 2:
- arrangement of equipment of basement premises;
- arrangement of commissioning works of ventilation and smoke removal systems;
- arrangement of commissioning works of fire alarm systems;
- arrangement of equipment of public places;
- arranging the equipment of the entrance group;
- installation of access control systems.
Building No. 3, Section 3:
- arrangement of equipment of basement premises;
- arrangement of commissioning works of ventilation and smoke removal systems;
- arrangement of commissioning works of fire alarm systems;
- arrangement of equipment of public places;
- arranging the equipment of the entrance group;
- installation of access control systems.
Improvements, building No. 3:
- improvement work continues along building No. 3;
- arranging a fence;
- landscaping of the territory continues;
- a rough layer of asphalt concrete covering is laid.
Building No. 4, Section 1:
- installation of K1, K2 risers and air conditioner drainage risers;
- arrangement of apartment wiring of water supply systems;
- arrangement of facades;
- arrangement of risers and apartment wiring of EO systems;
- work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof;
- installation of elevator equipment.
Building No. 4, Section 2:
- installation of K1, K2 risers and air conditioner drainage risers;
- arrangement of facades;
- work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof;
- installation of elevator equipment.
Building No. 4, Section 3:
- arrangement of facades;
- work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof;
- installation of elevator equipment.
Building No. 4, external networks:
- arrangement of external networks B1, K1, K2;
- connection of B1 systems to the city water supply network.
Building No. 5, Section 1:
- arrangement of vertical elements of the 8th floor;
- work continues on the installation of the floor slab of the 8th floor;
- arrangement of vertical elements of the 9th floor;
- installation of ventilation units and staircases.
Building No. 5, Section 2:
- arrangement of the floor slab of the 8th floor;
- arrangement of vertical elements of the 9th floor.
Building No. 5, Section 3:
- arrangement of monolithic walls, pylons of the underground part.
Building No. 5, parking lot:
- arrangement of vertical parking elements and waterproofing.
Building No. 6, Section 1:
- installation of technical superstructures on the roof;
- installation of roof waterproofing;
- installation of fans of smoke removal systems.