Construction progress for August 2023
04.09.2023
Eco-city LUCKY LAND by DIM is actively under construction! We are waiting for the certificate of readiness of the 3rd building, but we are not stopping for a moment in the construction of the entire block! Buildings 4, 5, 6 delight with their dynamics on the construction site.
We share a detailed report from the construction site for August:
Building No. 3, Section 1:
- arrangement of equipment of basement premises;
- arranging the equipment of the entrance group;
- arrangement of equipment of public places;
- installation of ventilation and smoke removal systems (commissioning works);
- installation of fire alarm systems (commissioning works);
- installation of a fire splinker fire extinguishing pumping station (commissioning works);
- installation of splinker fire extinguishing systems (commissioning works);
- installation of equipment in switchboards;
- arrangement of decorative plaster in MZK.
Building No. 3, Section 2:
- arrangement of equipment of basement premises;
- installation of ventilation and smoke removal systems (commissioning works);
- installation of splinker fire extinguishing systems (commissioning works);
- installation of equipment in switchboards;
- arrangement of equipment of public places;
- arrangement of decorative plaster in MZK;
- arrangement of equipment input group.
Building No. 3, Section 3:
- arrangement of equipment of basement premises;
- arrangement of equipment of public places;
- installation of ventilation and smoke removal systems (commissioning works);
- installation of splinker fire extinguishing systems (commissioning works);
- installation of equipment in switchboards;
- arrangement of decorative plaster in MZK;
- arrangement of equipment input group.
Improvement of railroad No. 3:
- landscaping along building #3;
- preparatory work for landscaping and entrance groups from the side of the inner yard.
Building No. 4, Section 1:
- installation of K1 risers and air conditioner drainage risers;
- preparatory work on the installation of risers and apartment wiring of power supply systems;
- installation of water pipe risers B1;
- laying water pipes in public places.
Building No. 4, Section 2:
- connection of external networks of water supply B1 is being performed;
- preparatory work is underway for screeding the floor;
- preparatory works for the installation of internal networks are being carried out;
- delivery of material for facade works, it is planned to start facade works from 20.09.
Building No. 4, Section 3:
- arrangement of facades;
- work is being carried out on the arrangement of finishing technical superstructures and ventilation shafts on the roof.
Building No. 4, external networks:
- arrangement of external networks B1, K1, K2;
- connection of B1 systems to the city water supply network.
Building No. 5, Section 1:
- arrangement of the floor slab of the 8th floor.
Building No. 5, Section 2:
- arrangement of vertical elements of the monolithic frame, 8th floor.
Building No. 5, Section 3:
- arrangement of concrete preparation of the foundation slab.
Building No. 5, parking lot:
- arrangement of the foundation slab of the parking lot;
- arrangement of vertical elements and waterproofing of the built-in TP.
House No. 6:
- connection of B1 systems to the city water supply network.
Building No. 6, Section 1:
- arrangement of parapets and technical superstructures on the roof;
- laying of internal walls and partitions on floors 5-9;
- arrangement of masonry ventilation shafts on the roof.
Building No. 6, Section 2:
- construction of internal walls and partitions from 4 to 14 floors continues.