Construction progress for August 2023

04.09.2023

Go back

Eco-city LUCKY LAND by DIM is actively under construction! We are waiting for the certificate of readiness of the 3rd building, but we are not stopping for a moment in the construction of the entire block! Buildings 4, 5, 6 delight with their dynamics on the construction site.

We share a detailed report from the construction site for August:

Building No. 3, Section 1:

  • arrangement of equipment of basement premises;
  • arranging the equipment of the entrance group;
  • arrangement of equipment of public places;
  • installation of ventilation and smoke removal systems (commissioning works);
  • installation of fire alarm systems (commissioning works);
  • installation of a fire splinker fire extinguishing pumping station (commissioning works);
  • installation of splinker fire extinguishing systems (commissioning works);
  • installation of equipment in switchboards;
  • arrangement of decorative plaster in MZK.

Building No. 3, Section 2:

  • arrangement of equipment of basement premises;
  • installation of ventilation and smoke removal systems (commissioning works);
  • installation of splinker fire extinguishing systems (commissioning works);
  • installation of equipment in switchboards;
  • arrangement of equipment of public places;
  • arrangement of decorative plaster in MZK;
  • arrangement of equipment input group.

Building No. 3, Section 3:

  • arrangement of equipment of basement premises;
  • arrangement of equipment of public places;
  • installation of ventilation and smoke removal systems (commissioning works);
  • installation of splinker fire extinguishing systems (commissioning works);
  • installation of equipment in switchboards;
  • arrangement of decorative plaster in MZK;
  • arrangement of equipment input group.

Improvement of railroad No. 3:

  • landscaping along building #3;
  • preparatory work for landscaping and entrance groups from the side of the inner yard.

Building No. 4, Section 1:

  • installation of K1 risers and air conditioner drainage risers;
  • preparatory work on the installation of risers and apartment wiring of power supply systems;
  • installation of water pipe risers B1;
  • laying water pipes in public places.

Building No. 4, Section 2:

  • connection of external networks of water supply B1 is being performed;
  • preparatory work is underway for screeding the floor;
  • preparatory works for the installation of internal networks are being carried out;
  • delivery of material for facade works, it is planned to start facade works from 20.09.

Building No. 4, Section 3:

  • arrangement of facades;
  • work is being carried out on the arrangement of finishing technical superstructures and ventilation shafts on the roof.

Building No. 4, external networks:

  • arrangement of external networks B1, K1, K2;
  • connection of B1 systems to the city water supply network.

Building No. 5, Section 1:

  • arrangement of the floor slab of the 8th floor.

Building No. 5, Section 2:

  • arrangement of vertical elements of the monolithic frame, 8th floor.

Building No. 5, Section 3:

  • arrangement of concrete preparation of the foundation slab.

Building No. 5, parking lot:

  • arrangement of the foundation slab of the parking lot;
  • arrangement of vertical elements and waterproofing of the built-in TP.

House No. 6:

  • connection of B1 systems to the city water supply network.

Building No. 6, Section 1:

  • arrangement of parapets and technical superstructures on the roof;
  • laying of internal walls and partitions on floors 5-9;
  • arrangement of masonry ventilation shafts on the roof.

Building No. 6, Section 2:

  • construction of internal walls and partitions from 4 to 14 floors continues.