Construction progress for July 2023

02.08.2023

Go back

LUCKY LAND by DIM is under construction. We share a detailed report from the construction site for July:

Building No. 3, Section 1:

  • hydraulic tests of external water supply networks;
  • work on the installation of external ETR networks is being carried out;
  • arrangement of equipment of basement premises;
  • arrangement of equipment input group;
  • installation of apartment meters for water supply accounting;
  • installation of apartment electricity meters;
  • arrangement of equipment for common areas, stairwells;
  • arrangement of ventilation and smoke removal systems;
  • installation of fire alarm systems;
  • installation of a fire splinker fire extinguishing pumping station;
  • installation of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • arrangement of decorative plaster in MZK;
  • installation of apartment doors.

Building No. 3, Section 2:

  • arrangement of equipment of basement premises;
  • arrangement of ventilation and smoke removal systems;
  • installation of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • arrangement of equipment for common areas, stairwells;
  • arrangement of decorative plaster in MZK;
  • arrangement of equipment input group;
  • installation of apartment doors;
  • installation of apartment meters for water supply accounting;
  • installation of apartment electricity meters.

Building No. 3, Section 3:

  • arrangement of equipment of basement premises;
  • arrangement of equipment of public places;
  • arrangement of ventilation and smoke removal systems;
  • installation of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • arrangement of decorative plaster in MZK;
  • arrangement of equipment input group.

Improvement of railroad No. 3:

  • landscaping along building No. 3;
  • preparatory works for landscaping and entrance groups from the side of the courtyard.

Building No. 4, Section 1:

  • preparatory work on the installation of risers and apartment wiring of systems B1, B2;
  • preparatory work for the installation of risers and K1, K2 systems;
  • preparatory work on the installation of risers and apartment wiring of power supply systems.

Building No. 4, Section 3:

  • arrangement of facades;
  • work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof.

Building 4, external networks:

  • arrangement of external networks B1, K1, K2;
  • connection of B1 systems to the city water supply network.

Building 5, section 1, 2:

  • arrangement of the floor slab of the 6th floor;
  • arrangement of vertical elements of the monolithic frame on the 7th floor;
  • arrangement of the floor slab of the 7th floor;
  • arrangement of vertical elements of the monolithic frame on the 8th floor.

Railway parking lot No. 5:

  • arrangement of concrete preparation;
  • arrangement of the foundation slab of the parking lot.

House No. 6:

  • connection of B1 systems to the city water supply network.

Building No. 6, Section 2:

  • the execution of brickwork of internal walls and partitions on the 6th-8th floors continues.

Building No. 6, Section 1:

  • arrangement of parapets and technical superstructures on the roof;
  • laying of internal walls and partitions on the 5th, 6th, 7th, 8th, and 9th floors;
  • arrangement of masonry ventilation shafts on the roof.