Construction progress for July 2023
02.08.2023
Go back
LUCKY LAND by DIM is under construction. We share a detailed report from the construction site for July:
Building No. 3, Section 1:
- hydraulic tests of external water supply networks;
- work on the installation of external ETR networks is being carried out;
- arrangement of equipment of basement premises;
- arrangement of equipment input group;
- installation of apartment meters for water supply accounting;
- installation of apartment electricity meters;
- arrangement of equipment for common areas, stairwells;
- arrangement of ventilation and smoke removal systems;
- installation of fire alarm systems;
- installation of a fire splinker fire extinguishing pumping station;
- installation of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- arrangement of decorative plaster in MZK;
- installation of apartment doors.
Building No. 3, Section 2:
- arrangement of equipment of basement premises;
- arrangement of ventilation and smoke removal systems;
- installation of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- arrangement of equipment for common areas, stairwells;
- arrangement of decorative plaster in MZK;
- arrangement of equipment input group;
- installation of apartment doors;
- installation of apartment meters for water supply accounting;
- installation of apartment electricity meters.
Building No. 3, Section 3:
- arrangement of equipment of basement premises;
- arrangement of equipment of public places;
- arrangement of ventilation and smoke removal systems;
- installation of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- arrangement of decorative plaster in MZK;
- arrangement of equipment input group.
Improvement of railroad No. 3:
- landscaping along building No. 3;
- preparatory works for landscaping and entrance groups from the side of the courtyard.
Building No. 4, Section 1:
- preparatory work on the installation of risers and apartment wiring of systems B1, B2;
- preparatory work for the installation of risers and K1, K2 systems;
- preparatory work on the installation of risers and apartment wiring of power supply systems.
Building No. 4, Section 3:
- arrangement of facades;
- work is being carried out on the arrangement of the decoration of technical superstructures and ventilation shafts on the roof.
Building 4, external networks:
- arrangement of external networks B1, K1, K2;
- connection of B1 systems to the city water supply network.
Building 5, section 1, 2:
- arrangement of the floor slab of the 6th floor;
- arrangement of vertical elements of the monolithic frame on the 7th floor;
- arrangement of the floor slab of the 7th floor;
- arrangement of vertical elements of the monolithic frame on the 8th floor.
Railway parking lot No. 5:
- arrangement of concrete preparation;
- arrangement of the foundation slab of the parking lot.
House No. 6:
- connection of B1 systems to the city water supply network.
Building No. 6, Section 2:
- the execution of brickwork of internal walls and partitions on the 6th-8th floors continues.
Building No. 6, Section 1:
- arrangement of parapets and technical superstructures on the roof;
- laying of internal walls and partitions on the 5th, 6th, 7th, 8th, and 9th floors;
- arrangement of masonry ventilation shafts on the roof.