Construction progress for March 2023
07.04.2023
Go back
Lucky Land from the DIM company is actively under construction. Building 3 is being prepared for commissioning. Preparatory works are being carried out for the installation of landscaping. Buildings 4 and 6 are undergoing facade work, laying walls, and installing elevator equipment.
We thank the investors for timely installment payments. You help keep Lucky Land's construction going fast.
March report on the construction of the best LUCKY LAND eco-complex:
Building No. 3, Section 1:
- work on the installation of external networks B1, K1, K2 is being carried out;
- work on the installation of external ETR networks is being carried out;
- arrangement of equipment of basement premises;
- equipment of the entrance group;
- installation of pumping equipment and water metering unit;
- equipping common areas;
- arrangement of ventilation and smoke removal systems;
- installation of fire alarm systems;
- installation of a fire splinker fire extinguishing pumping station;
- installation of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- installation of ceramic tiles in MZK.
Building No. 3, Section 2:
- equipment of basement premises;
- arrangement of ventilation and smoke removal systems;
- installation of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- equipping common areas;
- arrangement of ceramic tiles in MZK.
Building No. 3, Section 3:
- arrangement of equipment of basement premises;
- equipping common areas;
- arrangement of ventilation and smoke removal systems;
- installation of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- equipping common areas;
- arrangement of ceramic tiles in MZK.
House No. 4:
- work on the arrangement of the roof was carried out, the work was completed by 100%;
- facade insulation works are being carried out;
- work on the installation of elevator equipment continues.
House No. 6:
- works are being carried out on the arrangement of brickwork of internal walls and partitions on the 11th, 12th, 13th, 14th floors;
- installation of waterproofing of the roof and covers of ventilation shafts.