Construction progress for May 2023

06.06.2023

Go back

LUCKY LAND by DIM is actively under construction, the 3rd building is being prepared for completion of construction and obtaining a certificate of readiness. We are also building houses 4, 6 and have started building house No. 5.

We share a detailed report from the construction site for May:

Building No. 3, Section 1:

  • connecting the house to the city water supply network;
  • work on the installation of external ETR networks is being carried out;
  • arrangement of equipment of basement premises;
  • arranging the equipment of the entrance group;
  • installation of pumping equipment and water metering unit;
  • arrangement of equipment for common areas, stairwells;
  • arrangement of ventilation and smoke removal systems;
  • installation of fire alarm systems;
  • installation of a fire splinker fire extinguishing pumping station;
  • installation of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • installation of ceramic tiles in MZK;
  • installation of apartment doors.

Building No. 3, Section 2:

  • arrangement of equipment of basement premises;
  • arrangement of ventilation and smoke removal systems;
  • installation of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • arrangement of equipment for common areas, stairwells;
  • installation of ceramic tiles in the MZK, stairwells;
  • arrangement of equipment input group;
  • installation of apartment doors.

Building No. 3, Section 3:

  • arrangement of equipment of basement premises;
  • arrangement of equipment of public places;
  • arrangement of ventilation and smoke removal systems;
  • installation of splinker fire extinguishing systems;
  • installation of equipment in switchboards;
  • installation of ceramic tiles in the MZK, stairwells;
  • arrangement of furnishing works entrance to the parking lot;
  • arrangement of equipment input group.

Improvement of railroad No. 3:

  • landscaping along house #3.

Building No. 4, Section 1:

  • work on the installation of elevator equipment is being carried out;
  • work continues on the facades of the building.

Building No. 4, Section 2:

  • work continues on the facades of the building.

Building No. 4, Section 3:

  • arrangement of facades.

Building No. 5, Section 1-2:

  • installation work on the arrangement of staircases is being carried out;
  • the supply of ventilation units for the installation of ventilation ducts is in progress.

Building No. 5, Section 3:

  • preparatory works for the execution of the monolithic slab of the parking lot are underway.

Building No. 6, Section 1:

  • arrangement of parapets and technical superstructures on the roof;
  • installation of ventilation units;
  • laying of internal walls and partitions on the 11th, 12th, 13th floors.

Building No. 6, Section 2:

  • works are being carried out on the arrangement of brickwork of internal walls and partitions on floors 8-14;
  • arrangement of waterproofing covers of ventilation shafts;
  • installation of smoke exhaust fans on the roof.