Construction progress for May 2023
06.06.2023
Go back
LUCKY LAND by DIM is actively under construction, the 3rd building is being prepared for completion of construction and obtaining a certificate of readiness. We are also building houses 4, 6 and have started building house No. 5.
We share a detailed report from the construction site for May:
Building No. 3, Section 1:
- connecting the house to the city water supply network;
- work on the installation of external ETR networks is being carried out;
- arrangement of equipment of basement premises;
- arranging the equipment of the entrance group;
- installation of pumping equipment and water metering unit;
- arrangement of equipment for common areas, stairwells;
- arrangement of ventilation and smoke removal systems;
- installation of fire alarm systems;
- installation of a fire splinker fire extinguishing pumping station;
- installation of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- installation of ceramic tiles in MZK;
- installation of apartment doors.
Building No. 3, Section 2:
- arrangement of equipment of basement premises;
- arrangement of ventilation and smoke removal systems;
- installation of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- arrangement of equipment for common areas, stairwells;
- installation of ceramic tiles in the MZK, stairwells;
- arrangement of equipment input group;
- installation of apartment doors.
Building No. 3, Section 3:
- arrangement of equipment of basement premises;
- arrangement of equipment of public places;
- arrangement of ventilation and smoke removal systems;
- installation of splinker fire extinguishing systems;
- installation of equipment in switchboards;
- installation of ceramic tiles in the MZK, stairwells;
- arrangement of furnishing works entrance to the parking lot;
- arrangement of equipment input group.
Improvement of railroad No. 3:
- landscaping along house #3.
Building No. 4, Section 1:
- work on the installation of elevator equipment is being carried out;
- work continues on the facades of the building.
Building No. 4, Section 2:
- work continues on the facades of the building.
Building No. 4, Section 3:
- arrangement of facades.
Building No. 5, Section 1-2:
- installation work on the arrangement of staircases is being carried out;
- the supply of ventilation units for the installation of ventilation ducts is in progress.
Building No. 5, Section 3:
- preparatory works for the execution of the monolithic slab of the parking lot are underway.
Building No. 6, Section 1:
- arrangement of parapets and technical superstructures on the roof;
- installation of ventilation units;
- laying of internal walls and partitions on the 11th, 12th, 13th floors.
Building No. 6, Section 2:
- works are being carried out on the arrangement of brickwork of internal walls and partitions on floors 8-14;
- arrangement of waterproofing covers of ventilation shafts;
- installation of smoke exhaust fans on the roof.