LUCKY LAND
Construction progress for November 2025

08.12.2025

Go back

Sharing fresh news from the construction site for November:

Building #3, parking:

  • wall and column decoration – 100%

Building #4:

  • landscaping progress – 24%
  • installation of ventilation and supply systems – 90%
  • laying cables for street lighting – 25%
  • backfilling parking roof with soil – 65%

Building #4, section 1:

  • painting gypsum board ceiling in common areas from 3rd to 13th floor – 90%
  • laying ceramic tiles on staircases – 75%
  • installation of connections (SPOK) – 78%
  • installation of ventilation systems in the lobby – 100%
  • installation of control buttons in fire cabinets – 80%
  • facade finishing – 88%

Building #4, section 2:

  • installation of connections (SPOK) – 80%
  • staircase decoration – 90%
  • installation of ventilation systems in the lobby – 100%
  • painting gypsum board ceilings in common areas from 3rd to 13th floor – 90%
  • installation of control buttons in fire cabinets – 80%

Building #4, section 3:

  • installation of connections (SPOK) – 80%
  • installation of control buttons in fire cabinets – 80%
  • installation of SPS systems in the lobby – 50%

Building #6, section 1:

  • facade finishing – 32%

Building #6, section 2:

  • facade finishing – 94%
  • installation of ventilation shaft covers – 25%