Construction progress for November 2025
08.12.2025
Go back
Sharing fresh news from the construction site for November:
Building #3, parking:
- wall and column decoration – 100%
Building #4:
- landscaping progress – 24%
- installation of ventilation and supply systems – 90%
- laying cables for street lighting – 25%
- backfilling parking roof with soil – 65%
Building #4, section 1:
- painting gypsum board ceiling in common areas from 3rd to 13th floor – 90%
- laying ceramic tiles on staircases – 75%
- installation of connections (SPOK) – 78%
- installation of ventilation systems in the lobby – 100%
- installation of control buttons in fire cabinets – 80%
- facade finishing – 88%
Building #4, section 2:
- installation of connections (SPOK) – 80%
- staircase decoration – 90%
- installation of ventilation systems in the lobby – 100%
- painting gypsum board ceilings in common areas from 3rd to 13th floor – 90%
- installation of control buttons in fire cabinets – 80%
Building #4, section 3:
- installation of connections (SPOK) – 80%
- installation of control buttons in fire cabinets – 80%
- installation of SPS systems in the lobby – 50%
Building #6, section 1:
- facade finishing – 32%
Building #6, section 2:
- facade finishing – 94%
- installation of ventilation shaft covers – 25%