Construction progress for June 2025
30.06.2025
Go back
Sharing the latest news from the construction site for June:
Building No. 3:
- works are being carried out to lay down sewage pipes 0.4kV.
Building No. 3, section 1:
- the laying of ceramic floor and wall tiles in apartments from floors 27 to 32 has been completed, work is ongoing on floors 33-34;
- decorative plasterwork is being applied in apartments.
Building No. 3, section 2:
- decorative plasterwork is being applied in apartments;
- ceramic tile installation on balconies of the 4th floor is in progress;
- installation of the last 2 lifts is in progress.
Building No. 3, section 3:
- decorative plasterwork on walls (without painting) from floors 6 to 15 has been completed, work is continuing on floors 17-18;
- ceramic tile cladding is actively ongoing in apartments. Work on floors 3 to 17 has been completed, currently in progress on floors 18-34. Overall completion - 50%.
Parking garage No. 3:
work on waterproofing the parking slab is ongoing: installation of connections, pouring of lightweight concrete, membrane installation, drainage membrane and geotextile, reinforcement of protective slab and concreting. Completion - 75%.
Building No. 4, section 1:
- roof parapet installation;
- brick wall masonry completed from floors 28 to 31, work is ongoing on floors 32-33; ventilation block installation completed from floors 29 to 32 inclusive. Work is ongoing on floor 33;
- window structures installed from floors 5 to 12, work ongoing on floor 13.
Building No. 4, section 2:
- staircase construction completed from floors 4 to 9;
- brick wall masonry ongoing on floors 2, 3, and 5;
- ventilation block installation completed from floors 2 to 4, work ongoing on floor 5.
Parking garage No. 4:
- work in progress on waterproofing of columns, crossbars, and slab of crossbars;
- railing and crossbar installation ongoing, gravel backfill, sub-bulking, reinforcement and concreting of the parking slab;
- work ongoing on vertical structures of the parking garage and slab of the ceiling.