Construction progress for April 2023
26.04.2023
The modern innovative Metropolis project from the DIM company is actively under construction. We share the latest news from the construction site.
We report on the work done in April:
Building No. 3, Section 1:
arrangement of internal brick walls from the 1st to the 34th floor - 100%;
completed works on laying heating pipelines for apartments - 100%;
installation of fire valves per apartment - 100%;
installation of a cement-sand screed floor - 87%;
laying electrical networks (horizontal) for powering apartments and boilers, MZK - 90%;
installation of electrical panels has begun - 10%;
installation of internal water supply and sewage systems - 50%;
installation of a splinker system - 45%;
installation of elevator equipment - 15%.
Building No. 3, Section 2:
arrangement of internal brick walls from the 1st to the 11th floor - 100%;
laying of electrical networks (horizontal) for supplying apartments and boilers, MZK - 100%;
installation of internal water supply and sewage systems - 60%;
arrangement of LMM of the building - 55%;
installation of elevator equipment - 15%.
Building No. 3, Section 3:
arrangement of internal brick walls from the 1st to the 34th floor - 100%;
installation of fire valves per apartment - 100%;
installation of internal water supply and sewage systems - 60%;
laying of electrical networks (horizontal) for supplying apartments and boilers, MZK - 90%;
installation of electrical panels has begun - 10%;
arrangement of LMM - 55%;
laying tiles on the floor in the MZK - 55%;
installation of the splinker system - 80%;
installation of apartment doors - 40%;
installation of elevator equipment - 15%.
Railway station parking lot No. 3:
arrangement of ventilation system B-1-2-3-4-5-6-7-8, P-1 - 85%.
Building No. 4, Section 1:
reinforcement and concreting of vertical elements of the 14th floor building - 100%;
reinforcement and concreting of vertical elements of the 15th floor building - 85%;
arranging the brickwork of the 4th floor - 60%;
installation of staircases on the 10th floor - 100%;
installation of ventilation ducts on the 12th floor - 100%.
Landscaping:
works on the improvement of the 1st phase and the 3rd zone have been started.