Metropolis by DIM is being built at a fast pace!

We share the latest news from the site for October:

Building No. 3, Section 1:

  • laying electrical networks (horizontal) for lighting MZK - 50%;

  • arrangement of the NVF - 96%;

  • arrangement of SPOK - 92%;

  • installation of elevator equipment - 50%;

  • laying of low-current fire networks of the MZK - 40%.

Building No. 3, Section 2:

  • installation of elevator equipment - 45%;

  • installation of pipeline B1.2 – 90%;

  • laying electrical networks (horizontal) for lighting MZK - 90%.

Building No. 3, Section 3:

  • arrangement of LMM of the building - 77%;

  • laying tiles on the floor in the MZK - 95%;

  • installation of the fire protection system of the MZK, apartments - 50%;

  • installation of elevator equipment - 75%;

  • installation of metal entrance doors to the apartment - 96%.

Railway station parking lot No. 3:

  • arrangement of ventilation system B-1-2-3-4-5-6-7-8, P-1 – 94%;

  • decoration of the MZK of the basement residential part - 95%;

  • installation of engineering equipment in technical premises - 40%;

  • installation of main lines B1.2-B2.2 – 60%;

  • installation of smoke removal ducts - 30%.

Building No. 4, Section 1:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal elements of the building of the 20th floor - 30%;

  • arrangement of internal and external brick walls - 40%;

  • installation of staircases on the 15th and 16th floors - 25%;

  • installation of ventilation units - 45%.

Building No. 4, Section 3:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical elements of the 10th floor building - 100%;

  • reinforcement and concreting of vertical elements of the 11th floor building - 70%;

  • installation of ventilation units - 25%;

  • installation of staircases - 10%.

Railway station #4 parking lot, 2nd line, 2nd start:

  • reinforcement and concreting of horizontal and vertical structures - 30%.

Freestanding parking lot 3:

  • reinforcement and concreting of horizontal and vertical structures - 75%.