Construction progress for October 2023
01.11.2023
Metropolis by DIM is being built at a fast pace!
We share the latest news from the site for October:
Building No. 3, Section 1:
laying electrical networks (horizontal) for lighting MZK - 50%;
arrangement of the NVF - 96%;
arrangement of SPOK - 92%;
installation of elevator equipment - 50%;
laying of low-current fire networks of the MZK - 40%.
Building No. 3, Section 2:
installation of elevator equipment - 45%;
installation of pipeline B1.2 – 90%;
laying electrical networks (horizontal) for lighting MZK - 90%.
Building No. 3, Section 3:
arrangement of LMM of the building - 77%;
laying tiles on the floor in the MZK - 95%;
installation of the fire protection system of the MZK, apartments - 50%;
installation of elevator equipment - 75%;
installation of metal entrance doors to the apartment - 96%.
Railway station parking lot No. 3:
arrangement of ventilation system B-1-2-3-4-5-6-7-8, P-1 – 94%;
decoration of the MZK of the basement residential part - 95%;
installation of engineering equipment in technical premises - 40%;
installation of main lines B1.2-B2.2 – 60%;
installation of smoke removal ducts - 30%.
Building No. 4, Section 1:
Arrangement of s/b structures:
reinforcement and concreting of vertical and horizontal elements of the building of the 20th floor - 30%;
arrangement of internal and external brick walls - 40%;
installation of staircases on the 15th and 16th floors - 25%;
installation of ventilation units - 45%.
Building No. 4, Section 3:
Arrangement of s/b structures:
reinforcement and concreting of vertical elements of the 10th floor building - 100%;
reinforcement and concreting of vertical elements of the 11th floor building - 70%;
installation of ventilation units - 25%;
installation of staircases - 10%.
Railway station #4 parking lot, 2nd line, 2nd start:
reinforcement and concreting of horizontal and vertical structures - 30%.
Freestanding parking lot 3:
reinforcement and concreting of horizontal and vertical structures - 75%.